Ideas
Case files
16 real projects, walked through as lessons in judgment. Each tells what happened, then stops at the decisions the people in charge faced: what would you have done? The answer is folded away, with what came of it and the strongest case for the other choice.
-
Panama · 1881 to 1914
The Panama Canal
Two attempts to cut a canal through the Isthmus of Panama: a French one that collapsed after eight years, and an American one that finished in ten by changing the plan and fighting disease first.
3 decisions
-
Brazil · 1956 to 1960
Brasília
A new capital city built on an empty plateau in Brazil's interior in under four years, so that it would open before its president left office, and still growing in ways its plan never expected.
3 decisions
-
Sydney, Australia · 1957 to 1973
The Sydney Opera House
A building that opened ten years late at about fourteen times its first estimate, and that is now counted among the great buildings of the twentieth century.
3 decisions
-
Ghana · 1961 to 1966
The Akosombo Dam
A dam on the Volta River that gave newly independent Ghana its electricity and the largest reservoir in the world by area, built around a contract to power an aluminium smelter, and at the cost of some 80,000 people's homes.
2 decisions
-
Tanzania and Zambia · 1965 to 1976
The TAZARA railway
A railway of about 1,860 km from the coast of Tanzania to the copper belt of Zambia, built with Chinese money, engineers and workers when Western lenders said no, and run since by the two countries together.
3 decisions
-
Space, with mission control in Houston, United States · 1970
Apollo 13
A flight to the Moon that became a rescue when an oxygen tank burst: a study in how a team improvises under pressure, and in how the fault had been built in years before.
3 decisions
-
Worldwide, coordinated from Geneva · 1967 to 1980
The eradication of smallpox
The only human disease ever wiped out: a worldwide programme that shifted its weight from vaccinating as many people as possible to hunting down every case, and that had to prove a negative before it could call itself done.
3 decisions
-
London, United Kingdom · 1953 to 1984
The Thames Barrier
A movable flood barrier across the Thames, built three decades after a deadly storm surge, and now part of a flood plan meant to change as the sea rises.
3 decisions
-
India · 1970 to 1996
Operation Flood
A national programme that organised millions of small dairy farmers into village cooperatives and linked them to the cities, paid for at first by selling donated European milk powder, as India became the world's largest producer of milk.
2 decisions
-
Hawaiʻi to Tahiti · 1973 to 1976
The voyage of Hōkūleʻa, 1976
A volunteer society built a double-hulled voyaging canoe and sailed it about 4,000 km from Hawaiʻi to Tahiti, navigating without instruments, to show how the Pacific was settled, and learned that a project's purposes can pull its crew apart.
2 decisions
-
Bethel, New York, United States · 1969
Woodstock, 1969
A music festival that drew more than twice as many people as it had sold tickets to, moved to a new site a month before it opened, and turned into a free event on its first day, which became famous anyway.
3 decisions
-
Fremont, California, United States · 1982 to 2010
NUMMI, the Fremont car plant
A car plant closed for poor quality and worse labour relations, reopened by Toyota and General Motors with many of the same workers, which soon built cars nearly as well as Toyota's plants in Japan, while GM struggled to carry the lesson home.
3 decisions
-
Between Folkestone, England, and Coquelles, France · 1986 to 1994
The Channel Tunnel
Three tunnels under the sea between England and France: an engineering success that cost far more than planned and carried far fewer travellers than forecast.
3 decisions
-
London, United Kingdom · 1990 to 1992
The London Ambulance Service dispatch system
A computer system meant to send London's ambulances faster that failed within days of going live in 1992, and a public inquiry that became one of the most studied accounts of how a software project goes wrong.
3 decisions
-
Denver, United States · 1991 to 2005
The Denver airport baggage system
An automated baggage system so ambitious that the new airport around it opened sixteen months late, and that was finally switched off and replaced by ordinary conveyors.
3 decisions
-
Delhi, India · 1995 to 2006
The Delhi Metro, first phase
A city railway whose first phase opened section by section from 2002 and, by its builders' own account, finished ahead of schedule, in a country where large public works were known for running late.
3 decisions
Every case is told from published histories and official reports, listed on its page. Where a figure is disputed, or is only the project's own claim, the page says so.