Quest2PlanChart the course. Lead the crew.

Case file · Worldwide, coordinated from Geneva · 1967 to 1980

The eradication of smallpox

The only human disease ever wiped out: a worldwide programme that shifted its weight from vaccinating as many people as possible to hunting down every case, and that had to prove a negative before it could call itself done.

What happened

In 1966, smallpox was still endemic in about thirty countries and killed or disfigured millions of people every year. The World Health Assembly had resolved to eradicate it in 1959, but progress was slow. That year it voted for an intensified programme, starting in 1967, run by a small unit at the World Health Organization in Geneva, working through the health services of each country with staff drawn from dozens of nations.

The plan had two parts: mass vaccination, aiming to reach at least 80 per cent of people in each country, a target carried over from the earlier campaign, and the reporting and containment of outbreaks. At first the weight lay on vaccination. Better tools helped. Freeze-dried vaccine stayed potent for weeks in tropical heat, and a simple forked needle let workers with little training vaccinate quickly with less vaccine. Laboratories in endemic countries were helped to make vaccine of tested quality.

Early on, in eastern Nigeria, a field team short of vaccine tried another way: find every case quickly, isolate it, and vaccinate everyone around it. Transmission stopped there, with far fewer vaccinations than mass campaigns used. This approach, surveillance and containment, became the heart of the programme from about 1969. Success came to be measured not by how many people were vaccinated but by how fast new cases were found and how many outbreaks were contained.

The last cases came in the hardest places: the dense cities and villages of India and Bangladesh, and then the Horn of Africa, through war and drought. The last natural case of the dangerous form was in Bangladesh in 1975, and the last natural case of all was in Somalia in October 1977. After two more years of searching, with rewards offered for reporting any case, an independent commission certified the world free of smallpox, and the World Health Assembly declared it eradicated in May 1980.

The decisions

At each point, decide what you would do before opening the answer.

  1. 1966 to 1968

    Vaccinate everyone, or hunt the cases?

    Most of the effort went into vaccinating at least 80 per cent of every population. In some places, even high coverage did not stop the disease, and vaccine and staff were short. A team that had been forced to target its vaccine around outbreaks found that transmission stopped.

    What would you do? Do you keep the weight on the agreed approach, or shift it on the evidence of a few field teams?

    What they did, and what came of it

    The choice. Between 1967 and 1969 the programme moved its weight to surveillance and containment, while keeping vaccination going, and changed how its progress was measured.

    What came of it. The programme's effort went where the disease actually was. Its leaders credited the change, together with the better vaccine, for the speed of the end.

    The case for the other way. Changing strategy midway confuses staff and partners, and early field results can mislead. Containment needs good reporting, which some countries lacked; in dense populations, high coverage still mattered, and the two approaches worked best together.

  2. 1967 onwards

    What do you count as progress?

    Vaccination campaigns reported the number of people vaccinated. That number could grow while the disease went on spreading among those the campaigns missed.

    What would you do? Do you count the work done, or the result you want?

    What they did, and what came of it

    The choice. The programme came to judge itself by cases found, how quickly, and outbreaks contained, and sent assessment teams to check the figures in the field.

    What came of it. Hidden cases and weak reporting were exposed, and teams were sent where the counts showed the gaps.

    The case for the other way. Vaccinations are easy to count and to check; cases depend on reporting that can be poor or hidden for fear of blame, and a fall in reported cases can mean worse reporting rather than less disease.

  3. 1977 to 1980

    When is it really done?

    After the last known case, a single missed outbreak could restart the disease, and the world would stop vaccinating once eradication was declared.

    What would you do? Do you declare victory as soon as cases stop, or spend more time and money proving that none are left?

    What they did, and what came of it

    The choice. Two more years of active searching, rewards for reporting a case, international commissions to check country after country, and finally a global commission to certify the world.

    What came of it. The world was declared free of smallpox in 1980, and no natural case has been found since.

    The case for the other way. Every month of searching cost money and staff that other diseases needed, and rewards for reports bring many false alarms to check. But declaring too early, and stopping vaccination, would have risked everything.

What it teaches

A note on the figures

Counts of cases before the programme are estimates, since most cases were never reported. Who first tried surveillance and containment, and how much it alone explains the success, are debated; the programme's own history credits both it and continued vaccination.

Further reading

  • Smallpox and Its Eradication, Frank Fenner, Donald Henderson, Isao Arita, Zdeněk Ježek and Ivan Ladnyi (1988). The World Health Organization's full history of the programme.
  • Smallpox: The Death of a Disease, D. A. Henderson (2009). The programme's director on how it was run.

Cite or share this page

A plain reference you can paste into notes or an essay:

Quest2Plan. “The eradication of smallpox.” https://quest2plan.com/learn/ideas/cases/smallpox-eradication. Accessed 29 November 2026.