Case file · London, United Kingdom · 1953 to 1984

The Thames Barrier

A movable flood barrier across the Thames, built three decades after a deadly storm surge, and now part of a flood plan meant to change as the sea rises.

What happened

On the night of 31 January 1953 a storm surge swept down the North Sea and broke through sea defences in eastern England and the Netherlands. In England 307 people died; in the Netherlands more than 1,800. The water rose high in the Thames, and central London escaped by a narrow margin.

A government committee recommended a barrier across the river, but finding the right one took nearly twenty years. The Thames was then the route to one of the busiest ports in the world, so the river could not simply be closed. The design chosen used rising sector gates: curved steel gates that lie in concrete sills on the river bed, leaving the river open, and turn upwards to shut it.

Building began in 1974 at Woolwich, east of the city. The barrier became operational in 1982 and was formally opened in 1984, at a cost of about £535 million. It was designed to hold back a flood with a one-in-a-thousand chance in any year, allowing for the sea's rise over about fifty years. Looking further ahead, the Environment Agency later published a plan for the estuary that lays out several possible paths to the end of the century: whether and when to raise the river walls or build a new barrier is to be decided as measured sea levels show which path the world is on.

The decisions

At each point, decide what you would do before opening the answer.

  1. 1950s to 1960s

    Close the river, or keep it open?

    Among the early ideas was a fixed dam across the river with locks for ships, a familiar kind of structure. It would have slowed the ships of the Port of London.

    What would you do? Do you design round the river's biggest user, or round the most familiar safe solution?

    What they did, and what came of it

    The choice. Movable gates were chosen, leaving wide openings for ships when the barrier is not closed.

    What came of it. The river stayed open. But shipping was already moving downstream to deeper water, and by the time the barrier was finished most of the docks upstream of it had closed.

    The case for the other way. The port was then vital to the country's trade, and a design that hindered it would have met fierce opposition. The upstream docks were starting to close, but few foresaw how quickly the shipping would go.

  2. 1953 to 1972

    Build quickly, or take the time to get it right?

    Nearly twenty years passed between the flood and the law that allowed the barrier to be built, while the river walls were raised as a stopgap.

    What would you do? Do you act fast on an imperfect design, or take years to find a better one, knowing another surge could come?

    What they did, and what came of it

    The choice. The long route: studies, models, debate over sites and designs.

    What came of it. The barrier came about thirty years after the flood. Since then it has been closed against surges and river floods more than two hundred times.

    The case for the other way. A quick barrier in the wrong place, or of the wrong kind, would have been very hard to undo, and the time produced a new kind of gate that has worked well for decades. But for thirty years London depended on raised walls and on the weather.

  3. 2000s

    Build for the century now, or plan to adapt?

    Forecasts of sea-level rise over this century vary widely.

    What would you do? Do you build the big defence now for the worst case, or decide step by step as the evidence comes in?

    What they did, and what came of it

    The choice. The estuary plan sets out several paths, with decision points tied to measured sea levels and a review every few years.

    What came of it. Too early to judge. The barrier's own story shows how long big defences take to agree and build.

    The case for the other way. Waiting may leave too little time to build if the sea rises fast, and a step-by-step plan can become a reason never to decide. Building big early is expensive but certain.

What it teaches

  • Build for what you know, and write down what will trigger the next decision and who watches for it. Toolkit: Risk register
  • Assumptions about the world around a project, such as a busy port or a sea level, need an owner and a date to recheck. Toolkit: RAID log
  • A disaster that nearly happened is a warning to act on, not a relief. Toolkit: After-action review

A note on the figures

Cost figures for the barrier vary with what is counted (the gates alone, or the river walls raised downstream as well) and are in the money of the day, not adjusted for inflation.

Further reading

  • Thames Estuary 2100 Plan, Environment Agency (2012). The adaptive plan for flood defences to the end of the century.
  • The Thames Barrier, Stuart Gilbert and R. W. Horner (1984). An account of its design and construction, published by the Institution of Civil Engineers' press.