Apollo 13

A flight to the Moon that became a rescue when an oxygen tank burst: a study in how a team improvises under pressure, and in how the fault had been built in years before.

What happened

About fifty-six hours after launch, on the evening of 13 April 1970, Houston time, an oxygen tank burst in the service module of Apollo 13, on its way to the Moon. The command module lost most of its power and oxygen. The three astronauts, James Lovell, John Swigert and Fred Haise, moved into the lunar module, built to keep two people alive for about two days on the Moon's surface, and used it as a lifeboat for the four days around the Moon and home.

On the ground, flight controllers and engineers split the problem among teams: the course home, power, water, and how to restart a frozen command module for the return. When carbon dioxide began to build up, engineers designed, from materials on board, a way to fit the command module's square filters into the lunar module's round sockets, and read the steps up to the crew. The astronauts landed safely in the Pacific on 17 April.

The review board traced the cause. Switches inside the tank's heaters were rated for the spacecraft's 28-volt supply, but the heaters had been changed years earlier to run on 65 volts at the launch site, and the switches were never changed to match. Two weeks before launch, when the tank would not empty normally in a test, its heaters were left on for hours to boil the oxygen off. The switches welded shut, the temperature rose far past its limit, and the insulation on the wires inside was badly damaged. The tank had also been dropped a few centimetres at the factory in 1968.

The decisions

At each point, decide what you would do before opening the answer.

  1. Before launch

    Replace the tank, or fly it?

    In a ground test two weeks before launch, the oxygen tank would not empty in the usual way. Replacing it would have meant a costly delay to the launch.

    What would you do? Do you swap a part that behaves oddly but passes its checks, or work round the oddity?

    What they did, and what came of it

    The choice. The tank was emptied by leaving its heaters on for hours, and it flew.

    What came of it. The long heating, with switches that could not take the launch site's voltage, damaged the wiring that sparked the explosion in flight. Nobody running the test knew the switches were mismatched.

    The case for the other way. Removing and replacing a part brings its own risk of new damage, and a launch slip has costs of its own. Teams cannot replace every part that ever behaves unusually.

  2. Hour 56

    Turn back at once, or go round the Moon?

    The fastest way home was to turn round straight away, using the main engine on the damaged service module. That engine sat next to the explosion and could not be inspected, it needed electrical power the crippled spacecraft could hardly spare, and the burn would have meant casting off the lunar module, the only lifeboat.

    What would you do? Do you take the quicker route on an engine whose state you cannot know, or the slower one that avoids it?

    What they did, and what came of it

    The choice. Mission control chose to swing round the Moon, using the lunar module's own engine to adjust the course and later to speed the return.

    What came of it. The trip home took about four days on scarce power, water and oxygen, but did not depend on an engine that might fail or explode.

    The case for the other way. Every hour in the lifeboat used up supplies they were already short of, and nobody yet knew whether those would last. Had the engine and power been sound, the quicker route would have cut that risk by days. Here the case for it was weak, which is itself a lesson: some options look open only until you list what they need.

  3. From soon after the burst to re-entry

    Shut the command module down completely?

    The command module, the only part that could survive re-entry, had only its re-entry batteries left.

    What would you do? Do you keep some of its systems running so you know their state, or power it down completely and trust a cold restart?

    What they did, and what came of it

    The choice. It was powered down. Engineers on the ground wrote and checked a restart sequence that had never been tried, and read it to the crew before re-entry.

    What came of it. The cold, damp spacecraft came back to life and re-entered safely.

    The case for the other way. A cold restart had never been tested, and if it failed nothing else could bring the crew home. Keeping a few systems warm would have left a known, working state at the cost of some power.

What it teaches

Further reading

  • Report of Apollo 13 Review Board, NASA (1970). The official investigation, with the full chain of causes.
  • Lost Moon (later published as Apollo 13), Jim Lovell and Jeffrey Kluger (1994). The flight as the crew and the controllers lived it.