Case file · Tanzania and Zambia · 1965 to 1976

The TAZARA railway

A railway of about 1,860 km from the coast of Tanzania to the copper belt of Zambia, built with Chinese money, engineers and workers when Western lenders said no, and run since by the two countries together.

What happened

Zambia, newly independent and without a coast, earned most of its money from copper, and most of that copper went to the sea by rail through white-ruled Rhodesia. When Rhodesia's minority government declared itself independent in November 1965, Zambia's leaders wanted a route to the sea through friendly Tanzania instead. A study for the World Bank judged a railway uneconomic and recommended a road instead; a later British and Canadian study was more hopeful, but the World Bank and Western governments declined to pay for one.

China offered instead. In 1967 China, Tanzania and Zambia signed an agreement for an interest-free loan, repayable over decades, with Chinese engineers, workers and equipment to survey and build the line. Part of the local costs was met by selling Chinese goods in the two countries. Meanwhile, American money paved the road through the same corridor, and an oil pipeline was laid along the same route.

Building began in 1970 at Dar es Salaam and the track reached Kapiri Mposhi in central Zambia in 1975, through swamps, mountains and game country, with tens of thousands of Tanzanian and Zambian workers working beside Chinese workers who numbered more than ten thousand at the peak. By the usual account it was finished well ahead of its planned date. The line was handed over in 1976 to an authority owned jointly by the two countries.

It carried much of Zambia's trade through the hardest years. Traffic dipped when the southern route reopened in 1978, recovered to its highest in the late 1980s, and then fell steeply from the 1990s, as the end of apartheid and Namibia's independence opened other routes to the sea, lorries took more freight, and shortages of working locomotives and money for upkeep took their toll. China sent technical teams and funded repairs again and again. In the 2020s the two governments agreed to let a Chinese state company run and modernise the line under a long concession, while keeping its ownership. Freight trains still run, and passenger services between the two countries have run with interruptions.

The decisions

At each point, decide what you would do before opening the answer.

  1. 1965 to 1967

    Whose money, on whose terms?

    The World Bank and Western governments would not lend for a railway they judged uneconomic. China offered an interest-free loan, with its own engineers, workers and equipment, and with part of the cost met by selling Chinese goods in the two countries.

    What would you do? Do you take the one offer on the table, with the ties that come with it, or keep looking?

    What they did, and what came of it

    The choice. Tanzania and Zambia accepted, and the three governments signed the agreement in 1967.

    What came of it. The railway was built. It was then the largest single aid project China had undertaken abroad, and it tied the two countries to one partner for its running and repair for decades.

    The case for the other way. Depending on a single foreign partner, during the Cold War, carried political risk, and a loan repaid partly by buying the lender's goods shapes a country's trade. A paved road through the same corridor, which American money did pay for, together with the new pipeline, might have met the urgent need for less.

  2. 1970 to 1975

    Build fast, or build local skills first?

    The leaders of both countries wanted the line open as soon as possible. Chinese engineers and supervisors knew how to build it; few Tanzanians or Zambians had yet run a railway of this kind.

    What would you do? Do you let the experienced team run the work for speed, or slow it down to train the people who will inherit it?

    What they did, and what came of it

    The choice. Chinese teams led the technical and management work, while Tanzanian and Zambian workers learned on the job and in training schools, with the railway to be handed over after completion.

    What came of it. The line was finished quickly. Accounts of the handover describe too few trained local engineers and managers for the work ahead, and Chinese experts stayed on to help run and repair it for years.

    The case for the other way. Training a whole workforce first would have taken years that the crisis did not allow, and a railway that existed could be learned while it ran. Many who learned their trade on the line built careers on it.

  3. 1990s onwards

    Keep the line as it was built, or remake it for new traffic?

    As southern Africa changed, the crisis that justified the railway faded: other routes to the sea opened for Zambia's copper. Lorries on the road competed for freight, and the railway was short of working locomotives and money for repairs.

    What would you do? Do you keep a line built for an emergency running as it was, or change how it is owned, run and paid for to suit the traffic there now is?

    What they did, and what came of it

    The choice. For decades the two governments ran it themselves, with repeated rounds of Chinese help and refits, and plans for deeper reform were drawn up more than once. In the 2020s they agreed to hand its running and modernisation to a Chinese state company under a long concession.

    What came of it. Freight fell to a small fraction of what the line was built to carry, and it relied on outside help to keep running. It is too early to judge whether the concession will revive it.

    The case for the other way. Judged by its purpose, the railway did its job: it carried Zambia's trade when there was no other safe way. Infrastructure outlives the reasons it was built, and a line that exists can find new work, as regional trade grows.

What it teaches

  • Who pays shapes how the work is done. Read the terms of the money, not only the amount. Toolkit: Business case
  • Handing over a finished project means handing over the skills to run it, planned from the start. Toolkit: Handover plan
  • A project can be right for its moment and then lose its reason. Say what it is for, and check again later. Toolkit: Benefits review

A note on the figures

Figures vary between sources: the loan is usually given as about 988 million yuan, roughly 400 million US dollars at the time, and counts of the workforce differ widely. That the line was finished early is the usual account rather than a published comparison with a plan.

Further reading

  • Africa's Freedom Railway: How a Chinese Development Project Changed Lives and Livelihoods in Tanzania, Jamie Monson (2009). A history of the railway and the people who built and live along it.
  • The Great Uhuru Railway: China's Showpiece in Africa, Richard Hall and Hugh Peyman (1976). An account written as the line was finished.

Cite or share this page

A plain reference you can paste into notes or an essay:

Quest2Plan. “The TAZARA railway.” https://quest2plan.com/learn/ideas/cases/tazara-railway. Accessed 29 November 2026.