Business case
A short argument, made before the money is spent, that a project is worth its cost compared with the other ways of using the same people and money.
Who takes part
Sponsor Project lead Finance or budget holder Decision-makers
How to do it
- State the problem
Describe what is wrong or missing now, with a number if you have one: how many hours are lost, how many people are turned away, how much it costs.
- List the options
Set out two to four real ways forward, always including doing nothing and doing the least that would help. A case with one option is a sales pitch.
- Count the costs
For each option, estimate what it costs to make and what it costs to run afterwards, as a range rather than one hopeful number.
- Count the benefits
Say what each option would change, for whom and by when. Mark which benefits can be measured and which are judgement.
- Weigh the risks
Name the few things most likely to make each option cost more or deliver less, and how bad that would be.
- Recommend and say why
Pick one option and give the reasons in plain words, including what would make you change your mind.
- Revisit at checkpoints
When costs or benefits move a long way, check whether the case still holds. Stopping a project whose case has gone is a good decision, not a failure.
Where it goes wrong
- The decision is already made and the case is written afterwards to justify it.
- Doing nothing is left out, or described as a disaster so that any option looks better.
- Benefits are counted generously and running costs are forgotten.
- Nobody looks at the case again once the money is approved.
When to skip it
When the work is required by law or safety, or so small that the discussion costs more than the work, a few lines of why and how much are enough.
The one-page template
The headings to put on one sheet. Print it with room to write, or copy them into whatever your team already uses.
- The problem now
- Options, including doing nothing
- Cost to make and cost to run, per option
- Benefits, per option, and how we will measure them
- Main risks, per option
- Recommendation and reasons
- What would make us stop or change course
- Decision, by whom, and date