Case file · Between Folkestone, England, and Coquelles, France · 1986 to 1994

The Channel Tunnel

Three tunnels under the sea between England and France: an engineering success that cost far more than planned and carried far fewer travellers than forecast.

What happened

A tunnel under the Channel had been started and abandoned twice, in the 1880s and in 1975. In 1986 the British and French governments agreed to try again, on one condition, pressed above all by the British government and then written into British law: no public money and no government guarantees. A private company would raise the funds, have the tunnel built by a group of British and French builders, and then run it for decades to earn the money back.

Boring began from both coasts in 1987 and 1988. The service tunnels met under the sea in December 1990, the first land link between Britain and the continent since the Ice Age. Trains began running in 1994, about a year late. The project is three tunnels, two for trains and one between them for service and escape, about 50 km long, about 38 km of it under the sea.

Construction cost rose by about 80 per cent over the estimate, and with the interest on loans that grew with each delay, the total cost roughly doubled. The forecasts of passengers and freight that had persuaded investors proved far too high, partly because the ferries fought back with lower fares and larger ships. The owner's debts had to be restructured more than once, and early investors lost heavily. The tunnel itself works well and is an ordinary part of travel and trade across the Channel.

The decisions

At each point, decide what you would do before opening the answer.

  1. 1985 to 1986

    Public money or private?

    The British government would not pay for the tunnel. A private company could, if lenders and shareholders believed its forecasts.

    What would you do? Do you build a national link with private money and private risk, or not at all?

    What they did, and what came of it

    The choice. Wholly private financing, with the company carrying the risk of cost and traffic.

    What came of it. The tunnel was built, but each delay raised the interest bill, and the investors bore the losses.

    The case for the other way. Governments can borrow more cheaply and wait longer for a return. But private money kept the taxpayer out of the risk and put it on those who chose to take it, and imposed a discipline a public project might have lacked.

  2. 1988 to 1993

    Change the requirements during the build?

    Safety rules for the tunnel and its trains were set by a body of the two governments, which added and changed requirements while the work went on. The owner and the builders then disagreed about who should pay.

    What would you do? Do you freeze the rules early to control cost, or let safety requirements change as more is learned?

    What they did, and what came of it

    The choice. Changes were made as they came, and the cost of these and other disputed items was argued over afterwards, before a disputes panel, in arbitration and in the courts.

    What came of it. The tunnel opened with a strong safety design, but the disputes cost time, money and trust between the parties.

    The case for the other way. Freezing the safety rules early could have locked in a worse design for a hundred-year structure. When people's lives depend on the result, those setting the rules must be free to demand more.

  3. 1986 onwards

    How far to trust the forecast?

    Lenders and investors relied on forecasts of traffic and revenue made for the bid. Competitors, the ferry companies, would not stand still.

    What would you do? How much weight should a business case put on its own forecast of demand?

    What they did, and what came of it

    The choice. The forecasts were accepted, and the financing was built on them.

    What came of it. Revenue fell far below plan for years, and the owner's debts had to be restructured more than once.

    The case for the other way. Every large project rests on some forecast. Without a confident case no private money would have come at all, and the tunnel that exists carries millions of people and much freight every year.

What it teaches

  • Check a forecast against what similar projects actually achieved, not only against its own assumptions. Trap: Optimism bias
  • Agree before work starts how changes to requirements will be decided and paid for. Toolkit: Change request
  • A failed investment can still be a successful piece of infrastructure. Say which kind of success you mean. Toolkit: Business case

A note on the figures

Overrun figures depend on which estimate is the starting point and whether the cost of borrowing is counted. The figure of about 80 per cent is for construction cost in real terms, from Flyvbjerg and colleagues; counting financing, the overrun was larger.

Further reading

  • Megaprojects and Risk: An Anatomy of Ambition, Bent Flyvbjerg, Nils Bruzelius and Werner Rothengatter (2003). The Channel Tunnel among the large projects whose costs and forecasts the authors compare.
  • The Channel Tunnel Story, Graham Anderson and Ben Roskrow (1994). The project from agreement to opening.