Case file · London, United Kingdom · 1990 to 1992

The London Ambulance Service dispatch system

A computer system meant to send London's ambulances faster that failed within days of going live in 1992, and a public inquiry that became one of the most studied accounts of how a software project goes wrong.

What happened

The London Ambulance Service, the largest in the world at the time, sent its crews by hand: staff took emergency calls on paper forms, found the place in map books, and passed the forms to colleagues who kept track of each ambulance on paper and sent one by telephone or radio. A first attempt to computerise this was abandoned in 1990. The service started again, with a demanding plan: one system to take calls, track every ambulance by radio location, choose the nearest one and send it automatically. The contract was signed in August 1991, for a system due in January 1992; most bidders had objected to the timetable and were told it could not be changed.

The contract went to the lowest bidder, a group whose price was far below the others and whose software firm had no experience of emergency dispatch. The deadline was missed, parts of the system were tried during 1992, and on the morning of 26 October 1992 it took over the whole of London at once.

It depended on knowing exactly where every ambulance was and whether it was free, from radio location and from buttons the crews pressed. When that information was late or wrong, the system made poor choices, sent more than one ambulance or none, and filled screens with exception messages that staff could not clear. Callers waited, rang again, and added to the load. Within two days the service went back to a partly manual way of working, and the chief executive resigned. On 4 November the system stopped altogether, the untested backup failed, and the service went back to paper.

The inquiry for the regional health authority, published in 1993, found no single cause: an impossible timetable, a contract decided on price, software not fully tested or finished, staff and crews not fully trained and little consulted, and managers who believed the system would change working practices that it depended on. Some years later the service introduced a new computer dispatch system slowly, in small steps, with its staff, and it worked.

The decisions

At each point, decide what you would do before opening the answer.

  1. 1991

    The lowest price, on a fixed date?

    After the first failure, the service wanted a working system quickly and had to show value for public money. One bid was far cheaper than all the others, from a group whose software firm had never built a dispatch system.

    What would you do? Do you take the lowest bid on the date you need, or pay more, or wait longer, for a team that has done this before?

    What they did, and what came of it

    The choice. The contract went to the lowest bidder, with the original deadline.

    What came of it. The deadline was missed, and the system went live unfinished and not fully tested.

    The case for the other way. Public bodies are rightly pressed to spend money carefully, and a high price is no guarantee of quality. New suppliers have to start somewhere, and the larger bidders had no perfect record either.

  2. October 1992

    All at once, or in stages?

    Parts of the system had been tried, with problems, and managers wanted the new way of working in place.

    What would you do? Do you switch the whole city over at once, or bring it in area by area, with the paper system ready behind it?

    What they did, and what came of it

    The choice. The whole of London was switched to the new system on one day.

    What came of it. Its faults and the gaps in its data appeared everywhere at once, even on a lightly loaded morning. The paper backup had been taken out of the control room and the standby computer had never been tested; staff fell back on a semi-manual method only after a day and a half.

    The case for the other way. A dispatch system works on the whole fleet: sending the nearest ambulance means seeing all of them, so a part-city system has limits of its own, and running two systems at once carries its own risk of confusion.

  3. November 1992 onwards

    Fix it, or go back to paper?

    With the system failing, there was pressure both to repair it quickly and to restore a way of working that staff trusted.

    What would you do? Do you keep fixing the new system in service, or go back to the old way and start again more slowly?

    What they did, and what came of it

    The choice. The service returned to its manual system, and some years later brought in a new computer system step by step, with its staff.

    What came of it. The later system, built without a forced deadline and released in small steps, worked, and it is studied as the counterpart to the failure.

    The case for the other way. Going back throws away work and money, and the old manual system had its own delays and errors; it was why the service wanted computers in the first place.

What it teaches

A note on the figures

Unions and newspapers at the time claimed that delays caused by the failure had cost as many as twenty lives; the inquiry noted that no coroner had found a death caused by a late ambulance. The winning bid was about 937,000 pounds, some 700,000 below the next, but accounts of the price vary with what is counted.

Further reading

  • Report of the Inquiry into the London Ambulance Service, South West Thames Regional Health Authority (1993). The official inquiry, the main source for the case.
  • A comedy of errors: the London Ambulance Service case study, Anthony Finkelstein and John Dowell (1996). A short case study written for a software engineering workshop, widely used in teaching.