The planning fallacy

Also called: Inside view

We plan our own work from the best case and expect to finish sooner than similar work has ever taken.

What it is

The psychologists Daniel Kahneman and Amos Tversky gave the planning fallacy its name in 1979. When we plan, we picture our own project step by step: the tasks we know, done at a good pace, with nothing going wrong. That inside view feels detailed and therefore reliable. What it leaves out is everything we cannot picture yet: illness, delays, rework, a supplier who goes quiet. The same person who knows that most kitchen refits run late still expects their own to be on time, because this one has been thought through.

An example

In the 1970s Kahneman led a small team in Israel writing a school curriculum on judgement and decision-making. After a year he asked each member to estimate privately how long the rest would take; the answers clustered around two years. He then asked the team's curriculum expert, Seymour Fox, how long similar groups had taken. Fox recalled that about 40 per cent never finished, and none of the rest took less than seven years. The book took eight more years, and by then the ministry had lost interest in it.

How to spot it

Estimates are built only from a list of tasks, with no glance at how long the last few similar jobs took. Everyone's numbers cluster tightly together. Nobody can name a past project of this kind that finished as fast as the plan assumes.

The way out

Before trusting your own estimate, ask how long the last few jobs like this one actually took. Start from that record (the outside view), then adjust for what is truly different this time, and give the answer as a range rather than a single date.

When it is wise

A tight, hopeful plan can be a useful stretch goal inside a team, as long as the date promised to others comes from the record. And for truly new work with no record at all, a careful inside view is the best available.

Printable sheet of every technique

Cite or share this page

A plain reference you can paste into notes or an essay:

Quest2Plan. “The planning fallacy.” https://quest2plan.com/learn/ideas/traps/planning-fallacy. Accessed 29 November 2026.