The Planning Fallacy
In one line We plan our own work from the best case; asking how long similar jobs really took gives a truer estimate.
Ask people how long their next piece of work will take and most give an answer that is too short. They are not careless. They picture the work step by step, each step going about as well as it could, and add the steps up. What the picture leaves out is everything they cannot yet see: an illness, a late delivery, a part that has to be done twice.
In 1979 the psychologists Daniel Kahneman and Amos Tversky gave this habit a name, the planning fallacy: we judge our own plans from the best case and expect to finish sooner than similar work has ever taken, even when we know that most jobs like it ran late. In a well-known study published in 1994, the psychologists Buehler, Griffin and Ross asked students to predict when they would finish their final-year thesis. The average guess was about 34 days; the average actual time was about 55, and only about three in ten finished by the date they had named.
In his book Thinking, Fast and Slow, Kahneman described two ways of making a forecast. The inside view looks at this project: its tasks, its people, its plan. The outside view sets the details aside at first and asks how long the last few projects of the same kind took. The outside view feels crude, since it treats your careful plan as one more of its kind, but it is usually closer to the truth. Kahneman's advice was to start from it and then adjust for whatever is really different this time.
Earlier in the course, Drawing Time showed how a chart lays work out against the calendar; the planning fallacy is a reason to ask where its dates came from. The record is often unwelcome, and a team that has just made a careful plan rarely wants to hear it.
A kitchen before the holiday

Hiba is renovating the kitchen of her family's flat in Amman, Jordan. She lists every job: strip out the old units, move the sink, re-tile the walls, fit new cupboards, paint. Allowing a few days for each, she tells her mother-in-law the kitchen will be ready in five weeks, well before the family gathering for Eid.
Before booking the tiler, Hiba asks three neighbours in the building who redid their kitchens in recent years how long theirs took. The answers are eleven weeks, nine weeks and four months. Not one of them had planned for more than six. Hiba keeps her list, but she moves the gathering to her sister's flat, books the tiler early and tells the family to expect the kitchen after the summer. It is finished in ten weeks, and for once nobody is let down.
Try this today Think of something you plan to finish soon. Before you fix a date, recall how long the last two or three jobs like it actually took.
More on this trap: The planning fallacy →
A real project where it mattered: The Sydney Opera House →
A real project where it mattered: The London Ambulance Service dispatch system →
A real project where it mattered: The Denver airport baggage system →
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “The Planning Fallacy.” https://quest2plan.com/learn/lesson/the-planning-fallacy. Accessed 29 November 2026.
Sources
- Planning fallacy — The idea, its naming by Kahneman and Tversky, and the studies of students' thesis estimates.
- Reference class forecasting — The outside view put into practice: forecasting from the record of similar past projects.
- Daniel Kahneman — The psychologist's life and work, including Thinking, Fast and Slow.