Case file · Denver, United States · 1991 to 2005

The Denver airport baggage system

An automated baggage system so ambitious that the new airport around it opened sixteen months late, and that was finally switched off and replaced by ordinary conveyors.

What happened

Denver's new airport was planned as the largest in the United States. Two to three years after building began, the city decided to add one automated baggage system for the whole airport: thousands of small carts running on kilometres of track, sent by computers to carry each bag from check-in to its aircraft in minutes. A contractor agreed to design and build it in under two years, far less time than smaller systems of the kind had taken elsewhere.

The buildings were already partly built, so the track had to fit spaces not designed for it, with sharp turns and steep slopes. In tests in 1994, watched by the press, carts jammed, collided and threw bags out of them. The airport's opening, set for October 1993, was put off four times: the first two delays came from unfinished building work and training, the later ones mainly from the baggage system, while the finished airport stood empty.

In 1994 the city ordered a conventional backup of tugs, carts and conveyors. The airport opened in February 1995, with the automated system handling only one airline's departing bags in one concourse. It never worked as planned, and in 2005 that airline, judging it too costly to keep running, had it switched off.

The decisions

At each point, decide what you would do before opening the answer.

  1. 1991 to 1992

    Add an airport-wide system, late?

    The airport's buildings were designed and partly built. Each airline had expected to arrange its own baggage handling. An airport-wide automated system promised fast connections across a very large airport.

    What would you do? Do you add a large, new, critical system to a project already under way, on a schedule much shorter than similar systems have needed?

    What they did, and what came of it

    The choice. The city went ahead, with a schedule of under two years tied to the airport's opening date.

    What came of it. The system could not be finished, tested and made reliable in time, and the whole airport waited for it.

    The case for the other way. The case for automation was real: the distances were long, and an airline hub lives on quick connections. Smaller systems of the kind already worked elsewhere. The mistake, many argue, was not the idea but the schedule and the scale.

  2. 1992 to 1993

    Accept changes without moving the date?

    During the work, airlines and the city asked for changes to the system's layout and features, while the opening date stayed fixed.

    What would you do? Do you take the changes and hope to absorb them, or say what each one costs in time?

    What they did, and what came of it

    The choice. Changes were taken on, and the opening date stayed in place until the tests failed.

    What came of it. The work fell further behind, and the delay, when it came, came all at once.

    The case for the other way. The users of a system are the best judges of what it must do, and refusing their changes could have produced a system nobody wanted. Some change is the price of building something new.

  3. 1994

    Keep going, or open without it?

    After public failures in testing, the finished airport stood empty, costing large sums every month in interest and upkeep. The contractor argued that the system could be made to work.

    What would you do? Do you give the system more time, or pay for a backup and open without it?

    What they did, and what came of it

    The choice. The city ordered a conventional backup and opened with the automated system in limited use.

    What came of it. The airport opened. Researchers later used this choice as a leading example of how organizations can back out of a failing project.

    The case for the other way. The backup cost tens of millions and admitted failure in public. If the system had been close to working, every month of its success would have been worth a great deal, and the investment in it was already made.

What it teaches

  • A large new piece added late, into a schedule that cannot stretch, endangers everything that waits for it. Trap: Scope creep
  • A schedule far shorter than similar work has ever taken is a warning, not an achievement. Trap: The planning fallacy
  • Agree in advance on the point at which you will switch to a fallback, before the money spent makes that harder. Trap: Sunk cost and escalation
  • Imagine the failure before it happens, and plan the way back. Toolkit: Pre-mortem

A note on the figures

The often-repeated figure of about a million dollars a day for the delay was a popular estimate of the interest and running costs of the unopened airport, not all of it caused by the baggage system; the US General Accounting Office put the monthly shortfall at about 18 million dollars, nearer 600,000 a day. Figures for the system's own cost vary between sources.

Further reading

  • The baggage system at Denver: prospects and lessons, Richard de Neufville (1994). Journal of Air Transport Management 1(4); written while the airport stood unopened.
  • De-escalating information technology projects: lessons from the Denver International Airport, Ramiro Montealegre and Mark Keil (2000). MIS Quarterly 24(3); how the decision to back out was reached.

Cite or share this page

A plain reference you can paste into notes or an essay:

Quest2Plan. “The Denver airport baggage system.” https://quest2plan.com/learn/ideas/cases/denver-baggage. Accessed 29 November 2026.