Case file · Delhi, India · 1995 to 2006

The Delhi Metro, first phase

A city railway whose first phase opened section by section from 2002 and, by its builders' own account, finished ahead of schedule, in a country where large public works were known for running late.

What happened

Delhi, one of the fastest-growing cities in the world, had no metro, and its roads were choked. In 1995 the national government and the government of Delhi set up a company owned equally by both, the Delhi Metro Rail Corporation, to build and run one. It was given unusual freedom to hire, buy and decide without seeking separate approval at each step.

Building the first phase began in 1998. Much of the money came as long-term soft loans from Japan's state overseas lender (then called OECF, later JBIC, whose lending has since passed to JICA). The first section, about 8 km from Shahdara to Tis Hazari, was opened by the prime minister on 24 December 2002, and the first phase, about 65 km of lines, was finished in 2006. By the corporation's own account it was finished well ahead of its schedule. It cost about twice the estimate approved in 1996, but stayed within the revised budget approved as the network grew.

In its own and others' accounts, the corporation became known for its discipline on site: clocks in its offices counted down the days to each deadline; building sites in crowded streets were fenced, tidy and planned to keep traffic moving; and contractors were held to dates. Its record was not spotless. During later phases, construction accidents in 2008 and 2009 killed workers and passers-by and led to inquiries and changes in how sites were checked.

The decisions

At each point, decide what you would do before opening the answer.

  1. 1995

    A government department, or a company with its own powers?

    Large public works in India usually needed approvals from several ministries at each stage, and were known for delays.

    What would you do? Do you run a public project through the normal checks, or give its builders the power to decide for themselves?

    What they did, and what came of it

    The choice. A company jointly owned by the two governments, with the power to hire, buy and set its own procedures.

    What came of it. By most accounts decisions came quickly, and the first phase finished early by the corporation's own measure.

    The case for the other way. The usual checks exist because public money has often been misspent. A company with its own powers can escape scrutiny, and its success depends heavily on who leads it; the same freedom in other hands could have gone badly.

  2. 2000 to 2002

    Which width of track?

    The corporation wanted standard gauge, used by most metros in the world, for which modern trains were readily available. The national railway ministry insisted on broad gauge, the standard of India's main-line railways.

    What would you do? Do you match the world's metro market, or your own country's railways?

    What they did, and what came of it

    The choice. The national government decided for broad gauge in 2001, and after Delhi appealed, the prime minister's office confirmed it in 2002. The first phase was built in broad gauge; the lines built later mostly use standard gauge.

    What came of it. Delhi now runs a network with two gauges whose trains cannot run on each other's lines.

    The case for the other way. Broad gauge matched India's railway industry and workshops and kept open the option of linking with the main-line railway. Standard gauge matched the world's suppliers, and its supporters said it cost less per train. Both sides had a strong case.

  3. 1998 to 2006

    Put the deadline in front of everyone?

    In a culture where public works often slipped, the corporation wanted every worker and contractor to feel each date.

    What would you do? Do you make deadlines public and hard, or keep some room so that work is not rushed?

    What they did, and what came of it

    The choice. Countdown clocks, published dates, and contracts with penalties for missing them.

    What came of it. The first phase opened section by section, on or ahead of the corporation's own targets.

    The case for the other way. Hard public deadlines can push people to cut corners on safety and quality. After the accidents of later phases, critics asked whether schedule pressure had played a part; the inquiries blamed a failed lifting machine in one case and a design fault in the other.

What it teaches

A note on the figures

That the first phase finished ahead of schedule is the corporation's own measure, against targets revised as the network grew; the 1996 approval aimed to finish a smaller network by March 2005. India's national auditor records the approved cost rising from 4,860 to about 10,571 crore rupees. The Japanese lender's own evaluation rated the project highly. Schedules and budgets can be set, or reset, to be met.

Further reading

  • Project history and annual reports, Delhi Metro Rail Corporation. The corporation's own account, at delhimetrorail.com.
  • Ex-post evaluation of the Delhi Mass Rapid Transport System Project (I) to (VI), Japan International Cooperation Agency (2011). The lender's own evaluation of the loans for the first phase.
  • Performance audit of the Delhi Metro Rail Corporation (Report 17 of 2007-08), Comptroller and Auditor General of India. The national auditor on the first phase's cost and timing.