Traps · Guessing the future
Anchoring
Also called: Anchoring bias, the first number
The first number anyone says pulls every later estimate towards it, even when it was a guess.
What it is
Anchoring was described by Amos Tversky and Daniel Kahneman in 1974. In their experiments, people who had just seen a random number gave estimates that leaned towards it, even though they knew it meant nothing. In projects the anchor is usually a figure said early: a sponsor's hope, last year's budget, a rough guess made in a corridor. Everyone afterwards adjusts from that figure instead of working the answer out, and the adjustment is nearly always too small.
An example
A school governing board asks its head teacher how much a new science room might cost. Over coffee she guesses about forty thousand. Three months later the architect's careful estimate is sixty-five thousand, and the board treats it as an overrun, asking where twenty-five thousand has gone. Nothing has gone anywhere: the room was never going to cost forty. The first figure, said lightly, had become the measure every later number was judged by.
How to spot it
Someone asks "roughly how much?" before anyone has looked at the work. Later estimates are described as up or down from an earlier figure rather than built on their own. In estimating meetings, the first person to speak (often the most senior) sets the range everyone else stays in.
The way out
Do not let a number be said aloud until people have estimated on their own. Have each person write a figure privately and reveal them together, build estimates from the work rather than from a figure on the table, and label early guesses as guesses in writing.
When it is wise
An anchor drawn from good evidence, such as what the last five similar jobs cost, is a sound place to start. The trap is an anchor taken from a wish, a whim or a random guess.
Printable sheet of every technique
Cite or share this page
A plain reference you can paste into notes or an essay:
Quest2Plan. “Anchoring.” https://quest2plan.com/learn/ideas/traps/anchoring. Accessed 29 November 2026.