Lesson · 6 min Gentle
Estimating Together
In one line When a group estimates, each person should choose privately first, because the first number said aloud anchors the rest.
When several people will do the work, several people should estimate it. But a group can do worse than its members alone. The first number said aloud, often by the most senior or most confident person, becomes an anchor: everyone after adjusts from it instead of thinking afresh, and the adjustments are too small. In a 1974 experiment, Amos Tversky and Daniel Kahneman showed people a wheel rigged to stop at 10 or 65, then asked what percentage of United Nations members were African countries. Those who saw 10 gave a median guess of 25 per cent; those who saw 65, a median of 45.
Group estimating methods share one rule: estimate in private first, then compare. The Delphi method, developed at the RAND Corporation in the 1950s to forecast how technology might change warfare, collected anonymous estimates from experts, fed back a summary of the answers and reasons, and asked again over several rounds. In the 1970s Barry Boehm and John Farquhar adapted it for software as Wideband Delphi, adding discussion between rounds.
Planning poker, named by the software developer James Grenning in 2002, makes the same rule a card game. Each person holds cards whose numbers grow further apart (1, 2, 3, 5, 8, 13, 20) and picks one face down for a piece of work. Everyone turns their card at once. The highest and lowest explain their reasons, since one has often seen a difficulty or shortcut the others missed, and the group votes again. When the cards are close, it settles and moves on.
The gaps are the point: a spread from 2 to 13 means people pictured different work. The method fails when the lead says 'this looks like a three' before the cards go down, or when the numbers are later used to compare teams, which teaches people to inflate them.
The card that said twenty

Nilufar leads a small team at a seismology institute in the Uzbek capital, Tashkent, rebuilding the software that turns readings from forty stations into earthquake alerts. At the first planning meeting the director, a respected scientist, glanced at the first piece of work, merging the station feeds, and said, 'That's a week, surely.' Four people nodded.
For the next piece Nilufar handed out cards. Five came up, in days: 3, 3, 5, 5 and 20. The 20 belonged to the youngest programmer, who had once looked after the old station code; six of the stations, she explained, sent readings in a format nobody had written down. The others had not known. After a second round the cards settled on 13. Nilufar then took the director's 'week' for the feeds back to the cards, and the team agreed on three weeks. Merging the feeds took just under three.
Try this today Before your next group estimate, ask everyone to write a figure down before anyone speaks, then reveal them together.
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “Estimating Together.” https://quest2plan.com/learn/lesson/estimating-together. Accessed 29 November 2026.
Sources
- Planning poker — The card game for group estimates, its naming in 2002, and how it avoids anchoring.
- Delphi method — RAND's method of anonymous rounds of expert estimates with feedback.
- Anchoring effect — The bias by which a first number pulls later estimates, including Tversky and Kahneman's 1974 experiment.