Optimism bias
Also called: Rose-tinted planning
We expect good things to happen to our project and bad things to happen to other people's.
What it is
Optimism bias is the wider habit behind the planning fallacy: most people rate their own chances of success above the average and their chances of trouble below it. In projects it shows up as low costs, early dates and benefits that arrive in full. Optimism is pleasant and often rewarded: hopeful plans win approval, funding and volunteers, while cautious ones look weak. The researcher Bent Flyvbjerg, studying large public works, argues that optimism and deliberate low bidding together explain why so many run over budget.
An example
The Sydney Opera House was estimated in 1957 to cost 3.5 million pounds (seven million dollars in the decimal currency Australia adopted in 1966) and to open in January 1963. Work began in 1959, before anyone knew how to build the roof shells of Jørn Utzon's design. The engineering problems took years to solve, and the building was finally opened in October 1973 at a cost of about 102 million dollars, more than fourteen times the estimate. Today it is one of the best-loved buildings in the world.
How to spot it
Risks are listed but every one is marked unlikely. The budget has no contingency, or the contingency is the first thing cut. People who raise doubts are called negative. Benefits are counted in full and costs at their lowest.
The way out
Ask what usually goes wrong on projects like this, and plan as if some of it will. Keep a contingency that the plan does not quietly spend, invite someone outside the team to attack the estimate, and report a range, not the hoped-for number.
When it is wise
Some optimism is needed to start anything hard; the economist Albert Hirschman argued that underrating difficulty gets worthwhile projects begun, though later studies of large projects, by Flyvbjerg among others, found little evidence that such projects usually come good in the end. Hope is fine in the team's spirit. It does harm when it replaces the numbers given to the people paying.
Printable sheet of every technique
Cite or share this page
A plain reference you can paste into notes or an essay:
Quest2Plan. “Optimism bias.” https://quest2plan.com/learn/ideas/traps/optimism-bias. Accessed 29 November 2026.