Change request
A short written proposal to change what was agreed, so its cost, time and effect are understood before anyone says yes.
Who takes part
Person asking Project lead Sponsor or change panel Team Contractor or supplier
How to do it
- Write down the request
What should change, who is asking and why. 'Move the kitchen window thirty centimetres' is a change request; so is 'add Saturday sessions to the course'.
- Work out the effect
The people who would do the work estimate its effect on cost, dates, quality, risks and anything else already agreed or built.
- Offer options
Show more than yes or no: do it now, do it later, do a smaller version, or swap it for something else of similar size.
- Let the right person decide
Agree in advance who can approve changes of what size. The site lead may approve small ones; the sponsor or client decides the rest.
- Record the decision
Note the decision, the date and who made it. Under a contract, a signed change may also change the price and the finish date.
- Update the plan and tell people
Change the schedule, budget and drawings or documents, and tell everyone affected. A change approved but not passed on causes the next argument.
Where it goes wrong
- Small changes are agreed in corridors and on site visits, and nobody adds them up.
- The form becomes so heavy that people avoid it and make changes quietly.
- The cost is worked out but the delay is not, so the finish date silently slips.
When to skip it
On small, flexible work where change is expected, such as a cycle-based team with an ordered list, reordering the list is the change process; a formal request just slows learning.
The one-page template
The headings to put on one sheet. Print it with room to write, or copy them into whatever your team already uses.
- Request number and date
- Asked for by
- What should change, and why
- Effect on cost
- Effect on dates
- Effect on quality, risk and other work
- Options considered
- Decision, by whom, on what date
- Plans and people updated