Toolkit · Running
Burn-down and burn-up charts
A simple chart of work remaining, or work done against the total, over time, so a team can see whether it will finish when it hopes to.
Who takes part
Team Project lead Sponsor
How to do it
- Choose a unit of work
Count finished items, tasks or agreed sizes. Pick something that is either done or not done; half-finished work counts as nothing.
- Draw the axes
Time runs along the bottom in days or weeks. For a burn-down, the side shows work left; for a burn-up, it shows work done, with a second line for the total.
- Mark the start
Plot the starting amount and, if you like, a straight line to zero by the end date. That line is a reference, not a promise.
- Update it on a fixed day
Add a point at the same time each day or week, by hand on a wall chart or in a spreadsheet. Missed updates make the line meaningless.
- Track the total separately
When work is added, a burn-up shows the total line rising. A burn-down can hide new work, because finishing and adding cancel out.
- Read the trend together
Extend the line by eye to see where it meets the target. If it will not get there, talk now about scope, time or help.
Where it goes wrong
- Partly done work is counted, so the line looks good until the last week.
- New work is added quietly and the burn-down stays flat, so nobody sees the scope grow.
- The chart is used to compare teams or judge people, so the numbers start to be managed.
When to skip it
For a short job of a few days, or work with only a handful of large steps, a chart adds little; a dated checklist or a milestone plan shows progress just as well.
The one-page template
The headings to put on one sheet. Print it with room to write, or copy them into whatever your team already uses.
- What we count, and what counts as done
- Start date and target date
- Starting total
- Date, work done, work left, total
- Work added since the start
- What the trend says today