Status report
A short, regular note that says where the project stands, what changed, what is at risk and what help is needed.
Who takes part
Project lead Sponsor Team Stakeholders
How to do it
- Know who reads it
A sponsor wants decisions and risks; neighbours of a building site want dates and disruption. Write for the reader, and send different notes if the readers differ.
- Lead with the honest summary
Open with one or two sentences on where things really stand, including any slip. A reader who stops there should still know the truth.
- Say what changed
List what was finished, what moved and what was decided since the last report. Compare with the plan, not with last week's hopes.
- Show what is at risk
Name the top few risks and problems, what is being done about each, and whether they threaten a date, the budget or the quality.
- Ask for what you need
Say plainly what help or decision is wanted, from whom and by when. A report with no ask often hides one.
- Keep it to a page
Send it at the same rhythm each time, weekly or fortnightly, in the same shape, so readers learn where to look and notice when something is missing.
Where it goes wrong
- Every report says 'on track' until the week it says 'badly late'.
- It lists activity (meetings held, emails sent) instead of results.
- The colour rating is chosen to avoid an awkward conversation rather than to describe the work.
- Bad news is buried in the fourth paragraph in the hope nobody reads that far.
When to skip it
If the sponsor and team meet every few days and see the work themselves, a written report repeats what they already know; a few lines recording decisions and risks are enough.
The one-page template
The headings to put on one sheet. Print it with room to write, or copy them into whatever your team already uses.
- Project and date
- Overall: where we really stand
- Finished since last time
- Changed since last time
- Top risks and problems, with actions
- Help or decisions needed (from whom, by when)
- Next milestone and its date