Burn-down and Burn-up Charts

In one line A burn-down shows work left over time; a burn-up shows work done against a total, so added work shows.

A count of finished items becomes far more useful when it is drawn over time. A burn-down chart puts time along the bottom and the work still left up the side. Each day or week a point is added, and the line falls towards zero as items are finished. A straight line from the starting total to zero on the end date gives a reference: if the real line stays above it, the work is running behind.

The chart grew up with Scrum, the method that Jeff Sutherland and Ken Schwaber shaped in the early 1990s and presented at a conference in 1995. A Scrum team works in short cycles called sprints, often two weeks long, and a chart of the work left in the sprint became one of its most familiar tools. Nothing about it is tied to software: a choir preparing a concert or a crew fitting out a clinic can draw one on paper.

The burn-down has a blind spot. Suppose a team finishes five items in a week and the client adds five new ones. The line does not move, and the chart looks like a stalled team when the team worked well and the job grew. A burn-up chart separates the two. It draws work done rising from zero, and a second line for the total, which steps up whenever work is added. The gap between the lines is the work left. When the total keeps climbing, everyone can see that scope is growing, which is a conversation for the sponsor rather than a failing of the team.

Either chart is only as honest as its unit. Counting half-finished items lets the line look healthy until the end, and a chart used to rank teams soon starts to be managed rather than read. Read together, the trend asks the useful question early: at this rate, where will the line meet the target?

From sixty tasks to seventy-eight

Illustration: From sixty tasks to seventy-eight

Dauren coordinated the volunteers preparing a folk music festival in Almaty, Kazakhstan: sixty tasks over eight weeks, from booking the sound system to printing wristbands. He kept a burn-down chart on the office wall, and after four weeks it had fallen only from 60 to 48. The festival committee decided the volunteers were too slow and began to talk about hiring an events company.

Dauren redrew the same figures as a burn-up. The line of finished tasks had climbed to 30, exactly on pace. The total line, meanwhile, had stepped up from 60 to 78 as the committee added a children's stage, a second food court and a parade. The volunteers had done half the original work; the committee had added almost a third more. He laid the chart on the table at the next meeting. The committee dropped the parade and agreed that from then on, any new task had to replace one of similar size.

Try this today Count the open tasks on one list you keep. Note that number and the list's total each Friday for a month, and see which one moves.

In the Toolkit, step by step: Burn-down and burn-up charts →

Question 1 of 2

A team in Penang, Malaysia, building a hospital's appointment system sees its sprint burn-down stay flat for four days, although the developers say they have finished several items.

Why is the line most likely flat?

Question 2 of 2

Edgar, head of exams at a secondary school in Maputo, Mozambique, wants a burn-up chart for the forty tasks of the exam season.

Which order of steps sets the chart up soundly?

Cite or share this lesson

A plain reference you can paste into notes or an essay:

Quest2Plan. “Burn-down and Burn-up Charts.” https://quest2plan.com/learn/lesson/burn-down-and-burn-up. Accessed 29 November 2026.

Sources
  • Burndown chart — How a chart of remaining work is drawn and read, with a note on the burn-up variant.
  • Scrum (software development) — The method's history, its sprints, and the burn-down and burn-up charts teams keep.
  • Jeff Sutherland — The former military pilot and software developer who shaped Scrum with Ken Schwaber.