Case file · Ghana · 1961 to 1966

The Akosombo Dam

A dam on the Volta River that gave newly independent Ghana its electricity and the largest reservoir in the world by area, built around a contract to power an aluminium smelter, and at the cost of some 80,000 people's homes.

What happened

The idea of damming the Volta to power an aluminium industry dated from colonial times. After independence in 1957, Kwame Nkrumah's government made it the centre of its plans to industrialise. Ghana paid roughly half the cost itself and borrowed the rest from the World Bank, the United States and Britain. The loans depended on a long contract with an aluminium company controlled by American firms, which would build a smelter at the new port of Tema and buy much of the power.

Building began in 1961. The dam was finished in 1965 and formally opened by Nkrumah in January 1966, a few weeks before he was overthrown.

Lake Volta, filling behind it, became the largest reservoir in the world by area. It drowned about 740 villages. About 80,000 people were moved, most of them into 52 new resettlement towns built in a few years, with small core houses that their owners were expected to extend. Many settlers found too little farmland and moved away. The lake brought a new fishing industry and transport by water, and also a rise in water-borne disease along its shores.

For decades the smelter used most of the dam's power at a low price, and it worked with imported alumina rather than Ghana's own bauxite, so the chain of industry that had been hoped for did not follow. The power contract was renegotiated in the 1980s. The dam is still a main source of Ghana's electricity, and in dry years a low lake has meant power cuts.

The decisions

At each point, decide what you would do before opening the answer.

  1. 1958 to 1962

    Build around one big customer?

    Lenders wanted a buyer for the power secured by contract before they would lend. An aluminium company would take most of it on a long contract, at a low price, and bring its own raw material.

    What would you do? Do you accept a single big customer on its terms to get the project financed, or hold out for a better deal and risk having no dam?

    What they did, and what came of it

    The choice. Ghana signed the contract, and the loans followed.

    What came of it. The dam was built and the country gained a power supply. But the smelter's price stayed low for many years, and the hoped-for industry based on Ghana's own bauxite never came.

    The case for the other way. Without an anchor customer there would probably have been no loans and no dam at all. The smelter brought jobs and industry to Tema, and the contract could be, and later was, renegotiated.

  2. 1962 to 1966

    Move people fast, or slowly and well?

    The lake would rise on a timetable set by the dam. Farming and fishing communities in some 740 villages had to move before the water came.

    What would you do? Do you build fewer, larger new towns quickly, or rebuild each community more slowly, closer to how it lived?

    What they did, and what came of it

    The choice. A resettlement programme gathered the villages into 52 new towns, with small core houses and plans for new kinds of farming, all within a few years.

    What came of it. Many houses were left unfinished, the planned farming largely failed to arrive, and many settlers left. Researchers of resettlement have studied it closely ever since.

    The case for the other way. The timetable was set by the dam and the rains, not by the planners. Gathering people into larger towns made schools, clinics and clean water possible that hundreds of scattered villages would not have had.

What it teaches

  • One big customer can make a project possible and then shape it for decades. Read the long terms before you sign. Toolkit: Business case
  • Moving people is a project of its own, with its own budget, time and owners, and the people moved have a say. Toolkit: Stakeholder map
  • Count the side effects, good and bad, years after the ribbon is cut. Toolkit: Benefits review

A note on the figures

Figures vary between sources: the lake is usually given as about 8,500 square kilometres, and those moved as about 80,000 from about 740 villages (some sources say 700, others 756). Ghana's share of the cost depends on what is counted. How much of the power the smelter took, and at what price, changed over the years.

Further reading

  • A Dam for Africa: Akosombo Stories from Ghana, Stephan F. Miescher (2022). A history of the dam and of the people it moved.
  • The Volta River Project: A Case Study in Politics and Technology, David Hart (1980). How the project was negotiated and financed.