Benefits review

A check, made months after the project ends, of whether the change it was meant to bring has actually happened.

Who takes part

Sponsor People who run the result Users Reviewer

How to do it

  1. Plan it at the start

    When the business case is written, name each benefit, how it will be measured, its starting level and when it should appear.

  2. Name an owner

    Give each benefit an owner who stays after the project team leaves, usually someone who runs the result every day.

  3. Wait long enough

    Hold the review when the benefit could fairly have appeared: a few months for a new booking system, a year or more for a new clinic.

  4. Measure and compare

    Measure the same thing in the same way as at the start, and compare. Ask also what else changed that could explain the result.

  5. Look for side effects

    Ask users and neighbours what changed for them, good and bad, including results nobody planned.

  6. Decide what next

    If benefits fall short, decide what would help: training, a small fix, a change of use. Record what was learned for future business cases.

Where it goes wrong

  • Nobody measured the starting level, so there is nothing to compare with.
  • The review is never held, because the project team has gone and nobody owns the benefits.
  • Every gain is credited to the project, though other things changed at the same time.

When to skip it

When a project's only aim is to deliver a thing that is plainly needed (a replacement roof, a legal duty met), a later benefits review adds little. Checking acceptance is enough.

The one-page template

The headings to put on one sheet. Print it with room to write, or copy them into whatever your team already uses.

  1. Benefit expected (from the business case)
  2. How it is measured
  3. Level before the project
  4. Level now, date measured
  5. Other things that changed meanwhile
  6. Side effects, good and bad
  7. Owner of the benefit
  8. What we will do next

Print this template Every template, one to a page

Cite or share this page

A plain reference you can paste into notes or an essay:

Quest2Plan. “Benefits review.” https://quest2plan.com/learn/ideas/toolkit/benefits-review. Accessed 29 November 2026.