Toolkit · Finishing
Closure report
A short record written at the end of a project saying what was delivered, what it cost, what is left and what was learned.
Who takes part
Project lead Sponsor Team Finance
How to do it
- Compare with the start
Set the charter or business case beside what was delivered: the goal, scope, dates and budget. Say plainly what changed and why.
- Close the money
Pay final bills, close contracts and purchase orders, return unspent funds, and state the final cost against the budget.
- List what is left
Name anything unfinished, the open faults and the risks that remain, with who now owns each one.
- Store the records
Put the plans, decisions, contracts and acceptance papers where they can be found in five years, and say where in the report.
- Add the lessons
Summarize the main lessons in a few lines and add them to the lessons-learned register, rather than burying them here.
- Release the people
Agree with each person's manager when they move to new work, and thank them by name. Then formally declare the project closed.
Where it goes wrong
- The project is never formally closed; it fades away, and its budget and open contracts linger for years.
- The report is written to look good for the sponsor rather than to be true for the next team.
- Nobody records where the files are, and they are lost when the team moves on.
When to skip it
A small piece of work with no contracts, no separate budget and nothing left open needs no written report. An email saying it is done and where the files are will do.
The one-page template
The headings to put on one sheet. Print it with room to write, or copy them into whatever your team already uses.
- What we set out to do
- What was delivered
- Dates and cost: planned and actual
- What changed along the way, and why
- Items, faults and risks still open, owners
- Where the records are kept
- Main lessons (and where they are logged)
- Date the project closed