Project charter

One page, agreed at the start, that says why the project exists, what it will deliver, who leads it and what limits it works within.

Who takes part

Sponsor Project lead Core team

How to do it

  1. Say why

    Write the purpose in one or two sentences a newcomer would understand: the change the project should bring, not the thing it will make.

  2. Say what done looks like

    Name the main things to be delivered and how anyone will tell they are finished. A village well is done when it gives clean water, not when the hole is dug.

  3. Draw the edges

    List what is in and, just as plainly, what is out. The out-list settles arguments months later.

  4. Name the limits

    Write down the date, the money and anything else that cannot move, and say which of them matters most if something has to give.

  5. Name the people

    Who asked for it and pays for it, who leads it day to day, and who decides when the lead and the team disagree.

  6. Sign it together

    Sponsor and lead read it side by side and both agree. A charter nobody has said yes to is only a wish.

  7. Keep it in sight

    Pin it where the team works and reread it when a big decision comes up or the project starts to drift.

Where it goes wrong

  • The charter is written once and never read again.
  • The purpose is a list of outputs (a new building, a new system) with no word about why anyone wants them.
  • It runs to fifteen pages, so nobody reads it and nobody can quote it.
  • The lead writes it alone and the sponsor signs without reading.

When to skip it

For a job of a few days with one person in charge and an obvious goal, a short message saying what, by when and for whom does the same work.

The one-page template

The headings to put on one sheet. Print it with room to write, or copy them into whatever your team already uses.

  1. Project name and date
  2. Why we are doing this
  3. What we will deliver
  4. In scope
  5. Out of scope
  6. Fixed limits: date, money, other
  7. What matters most if something gives
  8. Sponsor, lead and who decides
  9. Agreed by (names and date)

Print this template Every template, one to a page

Cite or share this page

A plain reference you can paste into notes or an essay:

Quest2Plan. “Project charter.” https://quest2plan.com/learn/ideas/toolkit/project-charter. Accessed 29 November 2026.