Brasília

A new capital city built on an empty plateau in Brazil's interior in under four years, so that it would open before its president left office, and still growing in ways its plan never expected.

What happened

Brazil's first republican constitution, in 1891, called for a new capital in the interior, but for decades nothing was built. Juscelino Kubitschek won the presidency in 1955 promising fifty years of progress in five, and made the new capital his central goal. A state company was set up in 1956 to build it on the high, empty plateau of the centre-west, far from any railway or paved road.

In 1957 a jury chose the city plan of the architect and planner Lúcio Costa from a national competition. His entry was a short written report with freehand sketches: two crossing axes, one for the buildings of government, the other, gently curved, for housing in large blocks set in green space. Oscar Niemeyer designed the main public buildings. At first, materials came in by air and along rough tracks.

Tens of thousands of workers, many from the poor north-east of the country, came to build it, working in shifts by day and night. The city was inaugurated on 21 April 1960, with many buildings unfinished; ministries and embassies moved over the years that followed.

In practice the plan made no lasting place for the people who built the city: Costa foresaw satellite towns only once the centre had filled. The workers' camps and the towns that grew outside the plan, some founded in haste to rehouse squatters, became the satellite cities where most of the region's people now live. The plan was drawn for about half a million people; the metropolitan area now holds several million. The planned centre became a World Heritage site in 1987.

The decisions

At each point, decide what you would do before opening the answer.

  1. 1956 to 1957

    Build it within one presidential term?

    Kubitschek's term would end in January 1961. Earlier plans for an interior capital had come to nothing, and a later government might abandon this one too.

    What would you do? Do you set a date that makes the project impossible to stop, knowing it will force speed over finish?

    What they did, and what came of it

    The choice. A law of 1957 fixed the inauguration for 21 April 1960, and work went on round the clock to meet it.

    What came of it. The city opened on the date, unfinished. Critics blamed the rush, and the way it was paid for, for adding to Brazil's inflation, joking of fifty years of inflation in five; how much of the blame it deserves is still debated.

    The case for the other way. Brazil had talked about an interior capital for nearly seventy years without building one. A fixed date and a point of no return made it real, and the move did pull roads, farming and people towards the interior.

  2. 1957

    A sketch, or a full design?

    Some entries to the competition came with detailed studies of population, economy and growth. Costa's was a short report and a few drawings.

    What would you do? Do you choose the clearest idea, or the most fully worked-out plan?

    What they did, and what came of it

    The choice. The jury chose Costa's plan for the clarity and strength of its idea.

    What came of it. The city had a plan anyone could grasp, and work could start fast, with the details worked out as building went on. Critics say the hardest questions, such as where the workers would live and how people without cars would get about, were never answered.

    The case for the other way. Detailed entries had studied what the city would need; a sketch leaves those questions open. But a plan that tried to settle everything in advance might never have been built in the time there was.

  3. 1958 onwards

    Where do the builders live?

    Tens of thousands of workers and their families arrived. The plan had no room for them, and their camps were meant to be cleared once the city was built.

    What would you do? Do you keep the planned city as designed, or change the plan to make room for the people already there?

    What they did, and what came of it

    The choice. The authorities kept the plan and moved people to new satellite towns outside it, some founded in haste.

    What came of it. The capital grew as two cities: the planned, green centre, and a much larger, poorer ring of towns around it, linked by long journeys to work.

    The case for the other way. Keeping the plan protected the whole that made the city worth building, and new towns on open land could house people faster than an unfinished centre. Many satellite towns have since grown into cities with lives of their own.

What it teaches

  • A fixed date can make a project real; decide in advance what may be left unfinished to meet it. Toolkit: Milestone plan
  • A clear idea is not yet a finished design. Write down which questions it leaves open, and who will answer them. Toolkit: Scope statement
  • Map everyone the project will bring, including the people who build it, before the plan is fixed. Toolkit: Stakeholder map

A note on the figures

Accounts of what Brasília cost, and of how much it added to inflation, vary, and the blame is debated. Sources differ on the year by which the planned half million was expected, and population figures depend on whether the satellite towns are counted.

Further reading

  • The Modernist City: An Anthropological Critique of Brasília, James Holston (1989). How the plan and the city people actually built differ.
  • Relatório do Plano Piloto de Brasília (the pilot plan report), Lúcio Costa (1957). The winning competition entry: a short report with sketches.