Case file · Panama · 1881 to 1914

The Panama Canal

Two attempts to cut a canal through the Isthmus of Panama: a French one that collapsed after eight years, and an American one that finished in ten by changing the plan and fighting disease first.

What happened

In 1881 a French company led by Ferdinand de Lesseps, the celebrated builder of the Suez Canal, began digging a canal at sea level across the Isthmus of Panama, then part of Colombia. Suez had been cut through flat, dry desert. Panama was mountains, a river that flooded by metres in the wet season, and forest where yellow fever and malaria killed workers by the thousand. Landslides in the deepest cutting undid months of digging. The company collapsed and was dissolved in 1889. By one widely cited estimate, about 22,000 workers had died, most of them of disease.

The United States took over the works in 1904, after backing Panama's separation from Colombia the year before. Its first year went badly too. Then the new chief engineer, John Stevens, slowed the digging and put the effort into the railway, housing, water and supplies the work depended on, while the chief medical officer, William Gorgas, used the recent discovery that mosquitoes carry yellow fever to drive the disease out of the canal zone by the end of 1905.

In 1906 the US Congress chose a canal with locks over a sea-level one: a dam on the river would make a large artificial lake, and locks would lift ships up to it and lower them on the other side. When Stevens resigned in 1907, an army engineer, George Goethals, led the works to the end. The canal opened on 15 August 1914.

Most of the labour came from the Caribbean, above all from Barbados and Jamaica. These workers were paid in silver on a separate payroll from the mostly white Americans paid in gold, lived in worse housing, and accounted for most of the 5,609 deaths officially recorded in the American years.

The decisions

At each point, decide what you would do before opening the answer.

  1. 1879 to 1887

    Copy Suez, or design for Panama?

    At the congress in Paris that launched the project, de Lesseps pressed for a canal at sea level, like Suez. A French engineer, Godin de Lépinay, proposed instead to dam the river into a lake and reach it by locks, a plan suited to Panama's floods and hills.

    What would you do? Do you build the design that worked last time, or a different one for different ground?

    What they did, and what came of it

    The choice. The congress voted for a sea-level canal, and the company dug for one.

    What came of it. The cutting could not keep pace with landslides and floods. In 1887 the company switched to a temporary plan with locks, but it was too late and too short of money to finish.

    The case for the other way. A sea-level canal needs no water supply and has no locks to wear out, queue at or break down, and it was the design with a working example. Locks add time to every crossing and make a few structures critical to the whole canal.

  2. 1905

    Dig now, or prepare first?

    The American effort was stalling. Steam shovels stood idle for want of trains to carry the spoil away, yellow fever had broken out again, and workers were leaving. The people paying in Washington wanted to see the earth move.

    What would you do? Do you keep digging to show progress, or stop and build what the digging needs?

    What they did, and what came of it

    The choice. Stevens cut back the digging and spent many months rebuilding the railway, building housing, water supply and sewers, and organising supplies, while the campaign against mosquitoes went ahead.

    What came of it. When full digging resumed, the spoil moved, workers stayed and the death rate fell. The groundwork is widely seen as what made the ten-year finish possible.

    The case for the other way. Stopping visible work looks like failure to those paying, and support for the canal in Congress was far from certain. Preparation can grow into an end in itself, and digging early also teaches you about the ground.

  3. 1906

    Locks or sea level?

    A board of American and European consulting engineers recommended, by a majority, a canal at sea level. A minority, with Stevens, argued for a dam, a lake and locks.

    What would you do? Do you follow the expert majority, or the people who know this site?

    What they did, and what came of it

    The choice. Congress chose the lock canal.

    What came of it. The canal opened in 1914 and has run for more than a century. The lake that feeds the locks depends on rain: since the 2010s a third, larger set of locks has been added for bigger ships, and droughts in the 2020s forced limits on how many ships could cross.

    The case for the other way. A sea-level canal would never have needed new locks for bigger ships, would not depend on rainfall, and could not be put out of action by damage to one lock or dam. The majority were thinking of a canal for centuries, not decades.

What it teaches

  • A plan copied from an earlier success needs checking against this project's ground, climate and scale. Trap: Cargo-cult process
  • Building the means of doing the work (supply, housing, health) can be the fastest way to the work itself. Put that work in the plan where everyone can see it. Toolkit: Work breakdown structure
  • The people who carry the most risk are not always the ones counted in the plan. Map them. Toolkit: Stakeholder map
  • Money already spent did not make the French design right; the company kept raising more for it until it failed. Trap: Sunk cost and escalation

A note on the figures

The death toll of the French years was never counted: about 22,000 is an estimate, and others put it lower or higher. The American figure of 5,609 is the official count; the deaths of Caribbean workers, many of whom lived outside the canal zone, were probably under-recorded, and many historians think the true toll was higher.

Further reading

  • The Path Between the Seas: The Creation of the Panama Canal, 1870 to 1914, David McCullough (1977). The standard history of both attempts.
  • The Canal Builders: Making America's Empire at the Panama Canal, Julie Greene (2009). The workers' side of the American years.