Case file · Bethel, New York, United States · 1969

Woodstock, 1969

A music festival that drew more than twice as many people as it had sold tickets to, moved to a new site a month before it opened, and turned into a free event on its first day, which became famous anyway.

What happened

In early 1969 four young men formed a company to stage a three-day music and arts festival in upstate New York. Two had the money and two had the music contacts. They booked many of the best-known performers of the day and sold tickets in advance by mail and through record shops.

In July, a month before the festival, the town where it was to be held barred it. The organisers found a new site: a dairy farm near Bethel, some 50 kilometres away, whose owner agreed to rent his fields. Everything had to be rebuilt there in weeks: the stage, the roads, the water, the toilets, the food stands and the fences.

The organisers had planned for a large crowd, and sold some 186,000 tickets in advance. Somewhere between 400,000 and 500,000 people came. The roads for kilometres around jammed, and performers had to be flown in by helicopter. With the fences and ticket gates unfinished and the crowd already inside, the organisers announced on the first day that the festival was free.

Rain turned the fields to mud. Food, water and toilets ran short, and the small medical teams were overwhelmed; a few people died. A commune hired to run free kitchens and help keep order, local people who brought food, and Army helicopters that flew in doctors and supplies kept it going. The festival left its organisers deeply in debt, which was paid off over years, largely from the film and recordings of the event.

The decisions

At each point, decide what you would do before opening the answer.

  1. July 1969

    Move, or call it off?

    With a month to go, the town that was to host the festival barred it. Tickets were sold and performers booked.

    What would you do? Do you cancel or postpone, refunding the tickets, or find a new site and build everything again in weeks?

    What they did, and what came of it

    The choice. The organisers moved to a farm near Bethel and started building again.

    What came of it. The festival happened on its dates, but on a site with far less time to prepare than it needed.

    The case for the other way. Postponing would have cost money and goodwill, and might have ended the festival altogether. But a month was not enough to build safely for the crowd that came, and the risks fell on the audience.

  2. August 1969

    Finish the fences, or the stage?

    With days left, there were not enough people or hours to finish both the stage and the fences and ticket gates that would let the organisers control entry and collect money.

    What would you do? Which do you finish first, when you cannot finish both?

    What they did, and what came of it

    The choice. The organisers put their effort into the stage.

    What came of it. The music went ahead. The gates were never finished, and the crowd that arrived early made them pointless anyway: almost nothing was taken at the gate.

    The case for the other way. Without a stage there would have been no festival at all, and the fences could not have held back a crowd of that size anyway. Some argue the choice was the only one there was.

  3. 15 August 1969

    Fight the crowd, or let it in?

    Tens of thousands of people without tickets were already on the site, with more arriving, and no way to check tickets.

    What would you do? Do you try to clear people without tickets and enforce the gates, or declare the festival free?

    What they did, and what came of it

    The choice. The organisers announced from the stage that the festival was free.

    What came of it. Trying to clear the site was avoided, and the crowd stayed largely peaceful, but the organisers took on heavy debts.

    The case for the other way. A free festival invited still more people, who arrived to too little food, water and shelter. Holding the gates might have kept the crowd smaller and safer, if it could have been done at all.

What it teaches

  • Plan for the crowd that might come, not only the one you expect, and say what you will do if it does. Toolkit: Risk register
  • When time runs short, know which pieces everything else depends on, and finish those first. Toolkit: Critical path
  • Imagine the failure before the day: running out of water, roads blocked, a field of mud. Toolkit: Pre-mortem

A note on the figures

Crowd estimates for Woodstock range from about 400,000 to 500,000, and no one counted. Accounts of what the organisers expected, and of their losses, vary between their own memoirs and later histories.

Further reading

  • Young Men with Unlimited Capital, Joel Rosenman, John Roberts and Robert Pilpel (1974). Two of the organisers' account of the festival and its money.
  • Barefoot in Babylon: The Creation of the Woodstock Music Festival, 1969, Bob Spitz (1979). A history of how the festival was made.