Behavioural forecasting
Overview
People planning a project tend to picture how their own case will go and underestimate time, cost and risk, so forecasts should start from how similar projects actually turned out. Kahneman and Tversky named the planning fallacy in 1979, and Flyvbjerg tested it on megaprojects. Critics say some figures are contested and optimism also gets things built.
Behavioural forecasting applies research on judgement to the oldest questions in planning: how long will it take, and what will it cost? In 1979 the Israeli psychologists Daniel Kahneman and Amos Tversky named the planning fallacy: people forecast from the inside, imagining their own plan unfolding, and neglect how similar efforts went. Kahneman later told how a team he led in Israel, writing a school curriculum, expected to finish in about two years; a colleague who knew similar projects admitted that most had taken seven to ten years, and many never finished. The team carried on anyway, and the work took eight years. The Danish planner Bent Flyvbjerg later took these ideas to the study of large public works.
Read more (2 more paragraphs)
With colleagues, Flyvbjerg gathered data on hundreds of transport projects in many countries and found that cost overruns were the rule, with little sign of improvement over decades. In Megaprojects and Risk (2003) he argued that both optimism and strategic misrepresentation were at work. His remedy, reference class forecasting, starts from the outside view: what happened to projects like this one? Britain, Denmark and other governments built such checks into their appraisal guidance. The Sydney Opera House is a famous case: estimated in 1957 at about 7 million Australian dollars and due in January 1963, it was finished in 1973 at a cost of 102 million. How Big Things Get Done (2023), with Dan Gardner, advises planning slowly and building fast.
Critics say the overrun figures depend on which estimate counts as the baseline: measured from an early rough figure, almost every project overruns. Some construction researchers have challenged how Flyvbjerg's data were gathered and argued. The economist Albert Hirschman suggested in 1967 that a "hiding hand" of underestimation lets bold projects start that then find creative ways through, a claim Flyvbjerg has disputed with data. Choosing a fair reference class is itself a judgement. Defenders reply that the outside view is cheap, that it beats unaided judgement in the studies so far, and that it does not forbid ambition, only surprise. The habit worth keeping: before trusting your estimate, ask how long similar jobs really took.
Where it answers
Who should plan the work?
Whoever plans should first look up how similar jobs really went, and start the estimate there before trusting their own picture.
See how other practices answer “Who should plan the work?” →
When it goes wrong
At the estimate itself: the plan was probably too hopeful from the start, so compare it with what similar projects actually took.
Key terms
- Planning fallacy
- The tendency to underestimate the time, cost and risk of a planned task, even when similar tasks are known to have overrun.
- Inside view
- Forecasting from the details of one's own plan, imagining how this particular case will unfold.
- Outside view
- Forecasting from what happened in a class of similar cases, before adjusting for what is special about this one.
- Reference class forecasting
- Flyvbjerg's method: pick a class of past projects like yours, take their spread of outcomes, and place your forecast within it.
- Strategic misrepresentation
- Flyvbjerg's term for deliberately low estimates made to win approval, as distinct from honest optimism.
In their words
“He's taking an inside view. He should forget about his own case and look for what happened in other cases.”
Further reading
- Thinking, Fast and Slow · Daniel Kahneman
- Megaprojects and Risk: An Anatomy of Ambition · Bent Flyvbjerg, Nils Bruzelius and Werner Rothengatter
- How Big Things Get Done · Bent Flyvbjerg and Dan Gardner