Last Time, How Long?
In one line How long similar work really took before is often the best estimate, so keep a record of actual times.
Before guessing how long a job will take, ask a plainer question: last time, how long did it take? A record of how long similar work really lasted is often the most reliable estimate there is. It already contains the late deliveries, the sick days and the rework that a careful plan leaves out, because they actually happened.
Psychologists call this the outside view, and earlier in the course The Planning Fallacy showed why it tends to beat a detailed best case. Planners of large public works have turned it into a method, reference class forecasting: gather a set of past projects like this one, see how their times and costs were spread, and place the new project within that spread. In 2004 the British Department for Transport adopted it as official guidance for forecasting transport schemes. Software teams do a small version of the same thing when they measure how much work they finished in each of the last few fortnights, often called their velocity, and plan the next fortnight from that rather than from hope.
The catch is that the record must exist. Most organizations remember the plan and forget the actual. A task estimated at three days that took eight leaves no trace once it is done, so next year's estimate is made from the same hopes. Writing down what each piece of work really took, in a line or two at the moment it finishes, costs almost nothing and is worth keeping even when nobody asks for it.
History has limits. The past job must really be similar, and something may be truly different this time: a new material, a new team, a harder site. The usual advice is to start from the record and adjust for those differences, rather than start from the plan and adjust for the record.
Go deeper
A record stays useful only while it is honest, and it stops being honest the moment it is used to judge people. Software teams that measure their pace in points have found that once the figures are compared between teams or tied to praise, the points drift upward while the work stays the same. Any record of actual time can go the same way: if it is used to punish overruns, people start recording the plan instead of the truth. Records stay honest when they are kept for forecasting, and when a slow job is met with 'what made it slow?' rather than 'whose fault was it?'
The folder nobody asked for

Pablo works in the roads department of the city council in Córdoba, Argentina. The mayor wants to resurface forty blocks of a busy avenue before the winter holidays and asks how long it will take. The contractor's plan, built from crew sizes and asphalt deliveries, says eleven weeks.
Pablo opens a folder nobody had asked him to keep. For six years he has written down, for every resurfacing job, the blocks covered, the weeks planned and the weeks taken. Jobs of this size on avenues with buses had taken between fourteen and nineteen weeks, mostly because of night-work permits and old pipes found under the surface. He tells the mayor fifteen to nineteen weeks, likely sixteen, and suggests starting a month earlier than planned. The avenue reopens in week seventeen, inside his range and before the holidays.
Try this today Next time you finish a task you had planned, write down how long you expected it to take and how long it really took.
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “Last Time, How Long?.” https://quest2plan.com/learn/lesson/last-time-how-long. Accessed 29 November 2026.