Forecasting From What Already Happened
In one line Count what a team finishes each week and what is left, and you can forecast a range of dates without estimating tasks.
A team that keeps a record of what it finishes already holds a forecasting tool. Count the pieces of work finished in each of the last ten weeks. Count the pieces still to do. Divide one by the other and you have a rough forecast of how many weeks remain, made without asking anyone to estimate a single task. Earlier in the course, How Long Things Actually Take called this weekly count throughput.
Done properly, the forecast is a range, not a date. If a team finished between six and twelve pieces a week over the last ten weeks, and sixty remain, then at the slow end it needs about ten weeks and at the fast end about five. Most real outcomes fall between. The range is honest about the team's own ups and downs, and it updates itself: each finished week adds a new point to the record, so the forecast sharpens as the work goes on.
History is a good guide when tomorrow resembles yesterday: the same people, the same kind of work, pieces of roughly similar size, and a steady flow of new requests. It is a poor guide when something important changes. A new team, unfamiliar technology, a merger with another department, half the staff away for a holiday season, or a list full of pieces far larger than usual will all break the link between past and future. The list itself also tends to grow as people discover work they had not written down, so many teams allow for it.
Forecasting from history is still a forecast, and it rests on assumptions worth saying aloud: that the pace will hold, and that the list is roughly complete. Saying them lets others notice when they stop being true. Earlier in the course, Last Time, How Long? made the case for keeping such records at all; this is one of the best reasons to keep them.
Clearing the waiting list

Duangjai manages the physiotherapy clinic at a hospital in Chiang Mai, Thailand. Its waiting list holds 240 referrals, and a district health officer asks when it will be cleared. Instead of estimating each case, she opens the clinic's record. Over the last twelve weeks it closed between 35 and 50 referrals a week while about 25 new ones arrived, so the list shrank by roughly 10 to 25 a week. At that pace it will be cleared in about ten to twenty-four weeks.
She sends that range with two warnings. One of the clinic's three physiotherapists goes on leave next month, which will slow the pace, and the district plans to send referrals from two more villages, which will raise the arrivals. Either change would make the past twelve weeks a poorer guide. So she promises to redo the forecast each month from the most recent weeks, rather than defend her first answer, and the officer agrees to plan around the range.
Try this today Count the tasks you finished in each of the last four weeks, then divide what is left by your slowest and fastest week.
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “Forecasting From What Already Happened.” https://quest2plan.com/learn/lesson/forecasting-from-history. Accessed 29 November 2026.
Sources
- Forecasting — How forecasts are made from past data, and why they rely on past patterns continuing.
- Probabilistic forecasting — Forecasts that give likelihoods for a range of outcomes instead of one value.