Quest2PlanChart the course. Lead the crew.

Lesson · 6 min Stretch

The Cone of Uncertainty

In one line Early estimates can miss by a factor of four either way; the range narrows only as decisions get made.

At the very start of a project, before anyone has agreed what exactly will be built, an estimate of its cost can be wildly wrong. Barry Boehm, an American software engineer, gave this a shape in Software Engineering Economics (1981). He drew what he called a funnel curve: at the earliest stage the real effort might turn out anywhere from a quarter of the first estimate to four times it, and the range closes as the project moves through requirements, design and building. Steve McConnell later gave it the name now used, the cone of uncertainty.

The idea did not start with software. Cost engineers in the American chemical industry published classes of estimate with wide early ranges in 1958, and builders know the pattern well: a sketch of a school can be priced only roughly, a full design more closely, and measured quantities with suppliers' quotes more closely still. Earlier in the course, Ranges, Not Points argued for giving estimates as ranges; the cone suggests how wide they should be at each stage.

The cone has a catch that is easy to miss. It narrows because questions are answered: what the system must do, which site, which materials. Uncertainty shrinks through research and through decisions that remove a source of variation. A project that keeps putting decisions off, or keeps reopening them, stays at the wide end however many months pass. The calendar alone narrows nothing.

Critics say real projects rarely look so tidy. Boehm noted that his early ranges were set by judgement rather than measured. In 2006 Todd Little, working at a software company in Houston, compared its project estimates with the results and found that the spread of errors stayed about the same through a project's life instead of narrowing. Others point out that projects run late far more often than early, so the cone's neat symmetry flatters planners. Even its defenders call it a best case.

Go deeper

Why a quarter to four times, rather than, say, half to one and a half? Measured as ratios, the two ends are balanced: an estimate four times too low and one four times too high are mistakes of the same size. In money they are not. If the first estimate was 100 days, the low end saves 75 days while the high end costs 300 more. A planner who quotes the middle of such a range is still far more exposed on the costly side than on the cheap one, which is one reason early figures so often disappoint.

Two ranges in Almaty

Illustration: Two ranges in Almaty

Ainur works in the planning department of a city district in Almaty, Kazakhstan. In March she is asked for the cost of two things the district has barely described: a new primary school and an online system for parents to enrol their children. For the school she gives a range of half to twice her central figure. For the enrolment system, where nobody has said which schools will join or whether it must link to the national register, she gives a quarter to four times, and the deputy head of the district laughs.

Ainur explains what would narrow each range. Once the school's site is chosen and its soil tested, she can roughly halve its range; once the district decides which schools join the system and whether it links to the register, the software range should shrink too. Three months later the site is settled, but the register question has been to two meetings without a decision. Her school estimate is now tight, while the enrolment estimate is as wide as it was in March.

Try this today For one estimate you have given, write down which decision, once made, would narrow it the most.

Question 1 of 2

A roads agency in Lima, Peru, is asked to cost a ring road for which only the rough route is known.

Following Boehm's cone, what kind of estimate is most honest at this point?

Question 2 of 2

Six months into a hospital records project in Kuala Lumpur, Arif tells the board: 'We are halfway through, so by the cone our estimate must now be much more accurate.' The team has still not agreed which wards the system will cover.

What is wrong with Arif's reasoning?

Cite or share this lesson

A plain reference you can paste into notes or an essay:

Quest2Plan. “The Cone of Uncertainty.” https://quest2plan.com/learn/lesson/the-cone-of-uncertainty. Accessed 29 November 2026.

Sources