Monte Carlo in Plain Words

In one line A Monte Carlo simulation plays a plan out thousands of times with random durations and counts how often each date comes up.

Picture a small clinic building: foundations, walls, roof and fittings, each with a range of possible durations. No single estimate answers the question the owner cares about, which is how likely the whole building is to be ready by a given date. Adding the likely times gives one date, usually too early, because delays pile up while early finishes are small. Adding the worst cases gives a date so late nobody believes it. A Monte Carlo simulation finds the answer in between by brute force.

The idea needs no mathematics. For each step, write down its range, or better, the spread of how long such steps took before, as in Forecasting From What Already Happened. Then let a computer play the project out: for every step it picks a duration at random from that step's range, adds them up along the plan, and notes the finish date. It does this thousands of times. Each run is one possible version of the project; together they show how often each finish date turns up. If 85 per cent of the runs finish by the end of June, the honest summary is: about an 85 per cent chance of June, and some chance of later.

The method grew up at Los Alamos in the late 1940s. The mathematician Stanislaw Ulam, playing patience in 1946 while recovering from an illness, wondered about the chance of a game coming out and realized it was easier to play many games and count than to work it out. His colleague Nicholas Metropolis suggested the code name, after the casino in Monaco.

The output is only as good as the ranges put in. A simulation fed hopeful ranges produces a confident-looking picture of the same hopes, and one that treats linked risks as separate, such as two steps both held up by the same wet season, will make a very late finish look rarer than it is.

Go deeper

Why do the likely times, added up, give a date that is too early? Two reasons. Durations are lopsided: a step can rarely finish much sooner than usual, but it can run far later, so the overruns outweigh the gains. And where two paths of work run side by side and then join, the later of the two sets the pace, so the more paths that merge, the more likely one of them will hold things up. A simulation captures both effects without a formula. Earlier in the course, Three Numbers Are Better Than One gave each step a best, likely and worst case; those three figures are a common way to describe each step's range for a simulation.

A thousand soil studies

Illustration: A thousand soil studies

Fotima leads a soil study for a university in Samarkand, Uzbekistan. Her plan has two steps in a row. Collecting samples takes four weeks if the weather holds and six if it does not, and in past seasons each has happened about half the time. Analysis in the shared laboratory usually takes three weeks, but about one time in four the main instrument is booked by another team and it takes seven. Her first plan added the usual figures: seven weeks.

A colleague runs the plan a thousand times, tossing a virtual coin for the weather and drawing one card in four for the instrument. About 375 runs finish in seven weeks, about 375 in nine, about 125 in eleven and about 125 in thirteen. So seven weeks is a little under four chances in ten, nine weeks is about 75 per cent, and eleven about 88 per cent. Fotima tells the funder she is about 75 per cent confident of nine weeks, and that thirteen was the latest any run produced.

Try this today Toss a coin to choose fast or slow for each step of a small plan, ten times over, and tally the finish dates you get.

Question 1 of 2

Devika, a planner in Pune, India, reports that in a simulation of a new hospital wing, 85 per cent of the runs finished by the end of June.

What does Devika's result tell the hospital board?

Question 2 of 2

Evren, an engineer in Bursa, Turkey, is setting up a simulation for a new tram depot. His notes list four steps out of order: (1) count how often each finish date came up; (2) give each task a range of durations; (3) pick a random duration for each task and add them along the plan; (4) repeat that run thousands of times.

In what order should Evren carry out these steps?

Cite or share this lesson

A plain reference you can paste into notes or an essay:

Quest2Plan. “Monte Carlo in Plain Words.” https://quest2plan.com/learn/lesson/monte-carlo-plainly. Accessed 29 November 2026.