
Lesson · 6 min Stretch
Why Estimate at All?
In one line An estimate serves a decision, so the decision sets how much effort and precision the estimate deserves.
An estimate is never the point of the work. Someone asks for one because they have a decision to make: whether to start at all, how much to ask a donor for, when to book the hall, or how many people to hire. The estimate is an input to that choice, and it is worth only as much as it improves the choice.
That changes the first question a planner should ask. Not 'how long will this take?' but 'what will you decide with the answer, and how wrong could it be before you would decide differently?' A village committee wondering whether a new well is worth pursuing needs a rough range, perhaps within half or double. A contractor pricing a fixed bid needs far more care, since a small error comes out of its own pocket. Cost engineers in many countries grade estimates in this way, from a rough screening figure early on to a detailed check before a contract, and they expect the early ones to be wide.
Precision costs time. A detailed estimate for a building may take weeks of drawing, measuring and pricing; spent on a decision that a rough figure would have settled, those weeks are waste. Spared on a decision with a great deal of money riding on it, the saving is false. Earlier in the course, Ranges, Not Points showed that an honest estimate is a range; the decision tells you how narrow that range needs to be. Economists call the underlying idea the value of information: what it would be worth to know more before choosing.
Some decisions need no estimate at all, because the work will be done whatever it costs, or because it is small enough to try and see. That observation is the seed of a sharp debate about whether many estimates are worth making, which the rest of this week takes up.
Three sheets for four classrooms

Efua is the finance officer of a small education charity in Kumasi, Ghana, which wants to build four classrooms for a rural school. In one month three people ask her for an estimate. The board wants to know whether the project is within reach at all before it pays an architect. A foundation abroad wants a budget before it will consider a grant. A local contractor will later need firm quantities to price the job.
Efua answers each in a different way. For the board she takes the costs of two similar blocks the charity built nearby and gives a wide range, in a single afternoon. For the foundation she pays a quantity surveyor for a fuller estimate with a named contingency, which takes three weeks. On each sheet she writes which decision it is fit for. When a trustee later asks why the first figure was so rough, she reminds him that it only had to tell them whether to keep going.
Try this today Next time someone asks you for an estimate, ask what they will decide with it and how rough a figure would still do.
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “Why Estimate at All?.” https://quest2plan.com/learn/lesson/why-estimate-at-all. Accessed 29 November 2026.
Sources
- Cost estimate — How cost engineers grade estimates by purpose, from early screening to a detailed check before a bid.
- Value of information — The idea that knowing more is worth what it would change about a decision.
- Cone of uncertainty — Why early estimates are wide and narrow as a project becomes better defined.