Lesson · 6 min Stretch
Look at Projects Like Yours
In one line Forecast a project from how similar finished projects turned out, then adjust for real differences, not the other way round.
When people forecast their own project, they look at it from the inside: its plan, its team, its particular difficulties. Daniel Kahneman and Amos Tversky, the Israeli psychologists whose work on judgement under uncertainty changed how economists think about decisions, argued that this inside view leaves out the most useful information of all: how projects of the same kind actually turned out. In their writing on intuitive prediction in the late 1970s, they called the neglect of this information about similar cases a major source of error in forecasting. Earlier in the course, The Planning Fallacy described the optimism it produces.
Their remedy, which Kahneman later called taking the outside view, can be followed as a method. Pick a reference class: a set of finished projects truly like yours, such as urban rail lines or court buildings. Find how their final costs and durations compared with what was first forecast. Place your project in that spread, starting from the typical outcome, and only then adjust for what is really different about yours, with a reason for each adjustment.
The Danish planning researcher Bent Flyvbjerg developed this into a practical tool, reference class forecasting, for large public works. In 2004 Britain's Department for Transport adopted it in official guidance: rather than trusting a scheme's own cost estimate, planners add an uplift taken from how far similar schemes had overrun, larger or smaller according to how much risk of overspending the funders will accept.
The method has limits. Choosing the class is a judgement, and a promoter can pick flattering comparisons. A truly new kind of project has few peers. And the outside view feels unfair to a team proud of its plan. Its strength is that the record of similar projects already contains the surprises a plan cannot list.
Go deeper
In a study published in 2002, Flyvbjerg and two colleagues examined 258 transport projects worth about 90 billion US dollars, of different types, from different regions and periods. They found that the cost estimates used to decide whether to build them were, in their words, highly and systematically misleading, with costs underestimated far more often than not. They argued that honest error could not explain the pattern, and that deliberately low forecasts, which they called strategic misrepresentation, played a large part, a problem met earlier in When the Boss Wants a Smaller Number. The outside view guards against both the hopeful forecaster and the one with a reason to forecast low.
The rail line and its cousins

Dalal works for the transport authority in Amman, Jordan, which is weighing a new light-rail line. The engineers' estimate, built up carefully from track, stations, depot and signals, comes to 300 million dinars and four years. Before the board meets, Dalal gathers twelve finished urban rail lines in the region and beyond for which she can find both the first estimate and the final result. The typical one finished about 40 per cent over its first cost estimate and a year and a half late.
She does not throw out the engineers' work. She starts from the record, which suggests about 420 million and five and a half years, and then asks what is different here. The route runs mostly along an existing road, which lowers the risk; the land has not yet been bought, which raises it. Her paper to the board gives a range of 380 to 470 million and five to six years, with a note of what would move each figure.
Try this today Before your next estimate, find three finished jobs like it and note how far each ran over its first forecast.
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “Look at Projects Like Yours.” https://quest2plan.com/learn/lesson/projects-like-yours. Accessed 29 November 2026.
Sources
- Reference class forecasting — The method, its roots in Kahneman and Tversky's work, and its adoption in British transport guidance.
- Amos Tversky — His life and his long partnership with Daniel Kahneman on judgment under uncertainty.
- Underestimating Costs in Public Works Projects: Error or Lie? (Flyvbjerg, Holm and Buhl, 2002) — The study of 258 transport projects and its conclusion about misleading cost estimates.