
Lesson · 6 min Gentle
Power and Interest
In one line Sort stakeholders by their power over a project and its effect on them, then choose how to involve each.
A project touches more people than it can talk to often, so a lead has to choose where to spend time. A simple grid helps. One side measures how much power a person or group has over the project: can they stop it, fund it, approve it or slow it down? The other measures how much the project affects them, their stake in it. The grid is often called Mendelow's matrix, after the management scholar who set out a version of it in 1981.
Each corner suggests a way of working. People with high power and a high stake, such as the ministry funding an irrigation canal and the water users' association that will run it, are worked with closely. Those with high power but little stake, such as an office that must sign a permit, are kept satisfied: given what they need, without long meetings. Those with little power and a high stake, such as the farmers at the far end of the canal whose plots get water last, are kept informed and asked for their views. The rest are watched in case they move.
Two habits make the grid work. Give each important group one person on the team who keeps in touch with them, so nobody is forgotten and nobody is contacted by five people. And redraw it at each stage, because positions change: a quiet village can become powerful once it takes a complaint to the newspapers. Earlier in the course, Who It's For showed how to list the people a project serves; the grid helps decide how to treat each.
A grid is a start, not a verdict. It is easy to fill in from a meeting room by guessing, and to treat the low-power corner as the corner that matters least. The people with the most at stake and the least say are often the ones a project most needs to hear.
Go deeper
A grid also says something about the people on it, so handle it with care. Write down what each group wants and how the project affects them, not labels such as 'hostile' or 'difficult': a sheet like that tends to leak sooner or later, and does real harm when it does. Some teams add a third mark, whether each group supports the project, opposes it or has not yet made up its mind. That too is a guess, to be checked by asking the people concerned rather than filed as a judgement.
The far end of the canal

Kamola is the engineer leading the repair of an old irrigation canal in the Fergana Valley of Uzbekistan, paid for by the regional water authority. In her first week she listed everyone she could think of and drew the grid on the wall of the site office. The water authority and the district governor went in the top right corner. The large farms nearest the head of the canal went there too: they had money, loud voices and much at stake.
Then she walked to the far end of the canal, where small farms and household plots get water last, and in dry years not at all. Their owners had no seat on any committee, but the project mattered more to them than to anyone. Kamola put them in the low-power, high-stake corner and gave one of her technicians the job of visiting them every fortnight. It was the technician who learned that the planned closure of the canal for repairs fell right in their sowing season.
Try this today Draw a cross on a page. Label one line power and the other stake, and place five people your work touches. Who sits in the corner you talk to least?
In the Toolkit, step by step: Stakeholder map →
A real project where it mattered: The Panama Canal →
A real project where it mattered: Brasília →
A real project where it mattered: The Akosombo Dam →
A real project where it mattered: Operation Flood →
A real project where it mattered: The London Ambulance Service dispatch system →
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “Power and Interest.” https://quest2plan.com/learn/lesson/power-and-interest. Accessed 29 November 2026.
Sources
- Stakeholder analysis — How stakeholders are identified and sorted, including the power-interest matrix credited to Mendelow.
- Stakeholder management — The continuing work of identifying, assessing and engaging stakeholders, with a power-interest grid.