The Launch Decision

In one line Disasters often grow from small risks accepted so many times that they stop looking like risks at all.

On the evening of 27 January 1986, engineers at Morton Thiokol, which built the shuttle's booster rockets, joined a telephone conference with NASA about the next morning's launch of Challenger. It was forecast to be colder than any earlier shuttle launch. The engineers warned that the rubber O-rings sealing the booster joints might stiffen in the cold and fail to seal, and recommended not launching below 12°C (53°F). NASA managers on the call challenged their data. After a recess, Thiokol's own managers reversed the advice. Challenger lifted off at about 2°C and broke apart 73 seconds later. All seven people aboard died.

It is tempting to look for villains. The sociologist Diane Vaughan studied the records and, in The Challenger Launch Decision (1996), told a different story. Damage to the O-rings had been found after flights since 1981. Each time it was studied and judged acceptable, and the shuttle came home. Every safe return made the damage look a little more normal, and the line of acceptable risk moved. Vaughan called this the normalization of deviance. The people on the call had largely followed NASA's rules; the rules and habits themselves had drifted.

This does not mean nobody was responsible; some engineers and later writers held that the managers who overruled the warning must answer for their choice. Vaughan's point was that removing them would leave in place the culture that shaped them. Earlier in the course, Disagree and Commit used the same night to show a team talking itself out of its doubts.

In projects, danger rarely arrives as one dramatic decision. It builds up as a shortcut taken once, survived, and then taken as routine. The defence is to treat each departure from a standard as a question rather than a precedent: write it down, ask why it was safe, and change a rule openly when evidence says it should change. Newcomers help, since they still see what old hands no longer see.

Go deeper

The pattern returned. On 1 February 2003 the shuttle Columbia broke up on re-entry, and its seven crew died. A piece of insulating foam had struck its wing during launch. The investigation board, which included Diane Vaughan among its staff, found that foam had been shed on earlier flights too, and that managers had come to treat it as an accepted risk. The board judged that NASA's culture had contributed as much as the foam.

The alarm that always sounded

Illustration: The alarm that always sounded

Etenesh is chief engineer of a passenger ferry on Lake Tana, in Ethiopia. Its bilge alarm, which warns of water collecting in the hull, had sounded on almost every crossing for a year. The crew had learned to silence it: a little water was normal on an old boat, and the pump cleared it. Nobody remembered deciding that; it was simply how things were done.

Then a new deckhand, Fekadu, asked why an alarm that always sounded was there at all. Etenesh had no good answer. She asked the crew to log every silencing for a month, with the time and the depth of water. The log showed the water arriving faster each week. In dry dock the yard found a propeller shaft seal worn almost through. After the repair she made a rule: the alarm may be silenced only with a log entry and a look below, and any alarm silenced three times in a week goes to her.

Try this today Name one rule your team bends so often that nobody notices any more. Ask when anyone last checked that bending it is safe.

More on this trap: Normalization of deviance →

A real project where it mattered: Apollo 13 →

A real project where it mattered: The Delhi Metro, first phase →

Question 1 of 2

Nurses at a hospital in Amman, Jordan, have learned to override a drug pump's dose warning, because it fires for doses that are safe. Over a year the overrides grow from a few a week to dozens a day, and nobody looks into them.

What is happening on this ward, in Vaughan's terms?

Question 2 of 2

After a near collision in the harbour at Mombasa, Kenya, the port's report concludes: 'The duty pilot ignored the rules. Dismiss him and the problem is solved.' For two years pilots there had routinely taken the same shortcut through the channel.

What is the weakness in the report's conclusion?

Cite or share this lesson

A plain reference you can paste into notes or an essay:

Quest2Plan. “The Launch Decision.” https://quest2plan.com/learn/lesson/the-launch-decision. Accessed 29 November 2026.