Network diagram
A drawing of tasks as boxes and dependencies as arrows, showing what must wait for what and every route from start to finish.
Who takes part
Project lead Team Specialists
How to do it
- Start from the pieces
Take the lowest pieces of the work breakdown and write each on its own card or sticky note.
- Ask what must come first
For each card ask: what has to be finished before this can start? Walls before roof, permit before digging, paint after plaster.
- Draw the arrows
Lay the cards out from left to right and draw an arrow from each task to the ones that wait for it. Avoid crossing lines where you can.
- Mark outside dependencies
Show what the project waits for from outside, such as a delivery, an inspection or another team's work, in a different colour.
- Check the routes
Follow every path from start to finish. A card with no arrow in or out is either a start, an end, or a mistake.
- Add durations
Write the estimated time on each card. The diagram is now ready to find the critical path.
Where it goes wrong
- Dependencies that are only habits ("we always do the walls first") are drawn as if they were laws, and the plan loses room to move.
- People are treated as endlessly available, so two tasks that need the same electrician run side by side on paper.
- The diagram is drawn once and not redrawn when the order of work changes.
When to skip it
When tasks mostly run one after another or in a fixed routine, a simple list in order is clearer than a diagram.
The one-page template
The headings to put on one sheet. Print it with room to write, or copy them into whatever your team already uses.
- Project and date
- Task cards (number, name, duration)
- What each task waits for
- Outside dependencies (who, what, when)
- Start and finish points
- Notes on habits versus true dependencies
Cite or share this page
A plain reference you can paste into notes or an essay:
Quest2Plan. “Network diagram.” https://quest2plan.com/learn/ideas/toolkit/network-diagram. Accessed 29 November 2026.