Toolkit · Planning
Gantt chart
A bar chart of the schedule, with each task as a bar along a timeline, so anyone can see what happens when and what is running late.
Who takes part
Project lead Team Sponsor
How to do it
- List the tasks down the side
Use the pieces of the work breakdown, grouped by deliverable, so the chart can be traced back to the scope.
- Draw the time across the top
Pick a scale that suits the work, days for a festival week, weeks for a building, months for a programme.
- Draw the bars
Draw each task as a bar from its start to its finish, placed after the tasks it depends on.
- Show what links them
Draw thin arrows between dependent bars, or mark them some other way. A chart without links hides why dates are where they are.
- Mark the milestones and today
Add diamonds for the milestones and a vertical line for today, so progress and lateness can be read at a glance.
- Shade the progress
Fill each bar as work is done. Update it weekly and keep the original dates faintly visible for comparison.
Where it goes wrong
- The chart looks so neat that people treat guessed dates as certain.
- Dependencies are left off, so a slip in one bar seems to affect nothing else.
- It is drawn in great detail for a year ahead and never updated after the first month.
When to skip it
When work is planned in short cycles and the order keeps changing, a board of current work and a list of milestones shows more truth with less upkeep.
The one-page template
The headings to put on one sheet. Print it with room to write, or copy them into whatever your team already uses.
- Project and date of this version
- Tasks grouped by deliverable
- Time scale (days, weeks or months)
- Bars with start and finish
- Links between dependent tasks
- Milestones
- Today line and progress shading
- Changes since the last version