Drawing the Network
In one line A network diagram draws tasks as boxes and links as arrows, so every route from start to finish shows.
A list of forty tasks and sixty links cannot be held in anyone's head. A network diagram puts it on one page. Each task becomes a box, and an arrow runs from each task to every task that waits for it, so the drawing reads from left to right, from the start of the project to its end. Older diagrams drew the tasks on the arrows instead; most planners now draw boxes, a style also called activity on node.
Drawing one is simple work. Write each of the smallest pieces of work on its own card. For each card, ask what must be finished before it can start, as What Must Come First described. Lay the cards out and draw the arrows, untangling crossed lines where you can. Mark what the project waits for from outside, such as a delivery, an inspection or another team's work, in a different colour. Then follow every route from start to finish. A card with no arrow in or out is a start, an end or a mistake.
The picture shows things a list hides. Where the arrows split, work can run side by side. Where they meet, a task waits for everything that feeds it. And a long single line shows work that can only happen one piece after another, where extra people will not help much.
The diagram has limits. It shows order, not people, so two tasks that need the same electrician can look as if they run in parallel. Habits can be drawn as if they were laws. And a network drawn once and never redrawn soon describes a project that no longer exists. With a duration written on each card, though, the drawing is ready for the next step: finding the one route that decides how long the whole project takes.
A crossing on the branch line

Idris is the engineer for a level crossing upgrade on a branch line outside Tanta, Egypt: new barriers, new track panels and new signals where a busy road meets the railway. His task list ran to two pages. One evening he copied each task onto a card and laid them across the meeting room table with the two foremen.
The cards showed a shape nobody had seen. Once the road was closed, the work split into two routes, the track renewal and the barrier foundations, which could run side by side with separate crews, then met again at the signal test. Two cards went in red, because they depended on people outside the project: the railway's weekend track closure and the signalling team who had to test the crossing. And one card, moving the bus stop, had no arrows at all. Nobody had thought about it. It turned out the bus stop had to move before the road could close, and it needed the council's permission.
Try this today Take five tasks from something you are planning, write each on a scrap of paper, and lay them out with arrows. Where do the paths split?
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “Drawing the Network.” https://quest2plan.com/learn/lesson/drawing-the-network. Accessed 29 November 2026.
Sources
- Precedence diagram method — Drawing tasks as boxes and dependencies as arrows, also called activity on node.
- Arrow diagramming method — The older style, with tasks drawn on the arrows, and why boxes are now usually preferred.