Writing Down Your Assumptions
In one line Every plan rests on things taken for granted; list them, with who checks each and when, so they can be tested.
Every plan rests on things taken for granted. The seed arrives in March. The supplier keeps last year's price. The engineer who knows the old system stays to the end. The hall is still booked. None of these is written as a task, so none appears on the chart, yet if one fails, the tasks built on it fail too. An assumption is a risk in disguise.
The remedy is plain: write them down. For each one, note what the plan takes as true, who will check it, and by when. Once written, a hope becomes something the team can test. Some assumptions will be confirmed, some will turn out shaky, and a few will prove false while there is still time to act.
Many teams keep assumptions on one running list together with risks (what might happen), issues (problems happening now) and dependencies (what they wait for from others), often called a RAID log, and walk through it at the weekly meeting. Planners have built whole methods on the idea. Discovery-driven planning, set out by Rita Gunther McGrath and Ian MacMillan in 1995, judges a new venture less by whether it hits its forecasts than by how its assumptions hold up as facts arrive.
The hardest part is noticing what you assume. The dangerous assumptions feel like facts to the people who hold them, so they are the ones nobody thinks to write. Asking someone from outside the team, or asking 'what would have to be true for this plan to work?', brings more of them into the open. Replanning, as Changing the Plan Without Shame showed, is far easier when you know which guess failed.
Go deeper
Planners at the RAND Corporation published a method they called assumption-based planning, which defines an assumption as "an assertion about some characteristic of the future." Its steps run roughly: list the assumptions, judge which ones the plan most depends on, design a test or a sign to watch for each, check them on a schedule, and rework the plan when one fails. The same pattern turns up under other names in business and research, because every plan faces the same problem.
The truck that was always there

Baraka manages a farmers' cooperative near Arusha, Tanzania, which plans to grow a new bean variety for export this season. The plan was neat: land ready in February, planting in March, harvest in June, beans shipped through the port by July.
At the planning meeting, Baraka asked a different question: what are we taking for granted? The list ran to eleven lines. The seed arrives by early March. The rains start on time. The buyer keeps the agreed price. The cooperative's one truck is fit for the road to the coast. Each line got a name and a date for checking. The truck turned out to be the weak one: the mechanic said its gearbox would not last another season. Nobody had thought of it as part of the plan, because the truck had simply always been there. It was repaired in April, rather than found broken in July.
Try this today Ask of one plan you hold: what would have to be true for this to work? Write down three answers and who could check each.
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “Writing Down Your Assumptions.” https://quest2plan.com/learn/lesson/writing-down-assumptions. Accessed 29 November 2026.