Lesson · 6 min Gentle
Three Numbers Are Better Than One
In one line Ask for a best, a most likely and a worst case; the spread between them shows where the risk lies.
When there is no record to lean on, a single guess is the weakest kind of estimate. A stronger one asks three questions instead of one. How long if things go well, though not miraculously? How long does work like this normally take? And how long if the common troubles arrive: the delivery is late, the ground is harder than expected, the specialist falls ill? The answers are the best case, the most likely case and the worst case.
The idea has a military history. In 1958 the United States Navy's Special Projects Office, planning the Polaris missile programme, needed a way to schedule work nobody had done before. The method developed for it, the Program Evaluation and Review Technique or PERT, asked for three time estimates for each activity and combined them with a simple formula: the best case, plus four times the most likely, plus the worst case, all divided by six. The weighting leans on the most likely figure but lets a long worst case pull the answer later, which matches how delays behave: a job can rarely finish much early, but it can finish very late.
The formula is the least important part. The gap between best and worst shows how uncertain each piece is, and asking for the worst case gives people permission to say what worries them. 'Why could this take nine weeks?' starts a conversation about risks that a single number never would, and the answers belong in the plan as the things to watch.
Three-point estimates go wrong in familiar ways. The worst case is written as the likely case plus a little, so the range looks safe and narrow. The middle number travels to the next meeting and the range is forgotten. And the numbers are only as good as the people who give them, which raises the question of who should estimate.
Go deeper
PERT also gives a rough measure of spread for each piece: the worst case minus the best case, divided by six. Planners used it to judge how likely a whole programme was to finish by a given date, adding up the pieces along the longest chain of work. The arithmetic assumes the pieces are independent, so that one running late does not make the next run late too. In real projects delays often travel together: the same rain soaks every site, the same late supplier holds up three tasks. So a combined range from the formula tends to be narrower than the truth, and careful planners treat it as the least uncertainty to expect, not a measurement of it.
A bridge by the evening

Ngozi, a lieutenant in an army engineer unit, is planning a field exercise near Tamale, in northern Ghana. Her platoon must put a light bridge across a river and have vehicles crossing by a set hour. Her commander asks how long the bridge will take to build. Her first thought is six hours.
Instead she asks her two sergeants for three figures. Best case, with dry banks and every part on the first lorry, four hours. Most likely, six. Worst case, if the banks are soft and need shoring and a lorry is late, fourteen. The formula gives (4 + 24 + 14) / 6, which is seven hours. More useful was the talk the fourteen started: the sergeants knew the banks crumble after rain. Ngozi sends a team the day before to test them, reports 'four to fourteen hours, plan on seven', and the commander moves the crossing to the evening.
Try this today Pick a job you face this week. Write how long it takes if it goes well, how long it usually takes, and how long if the usual trouble strikes.
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “Three Numbers Are Better Than One.” https://quest2plan.com/learn/lesson/three-numbers. Accessed 29 November 2026.