Lesson · 6 min Gentle
The Critical Path
In one line The longest chain of linked tasks sets the shortest time a project can take, so delay there moves the end.
Once every task in a network has a duration, one chain through it decides how long the whole project takes. It is the longest chain of tasks that each wait for the one before, from start to finish, and it is called the critical path. The longest route through the work sets the shortest time the project can take, because nothing can finish before that chain does.
The method was worked out in the late 1950s by two engineers, Morgan Walker of the chemical firm DuPont and James Kelley of Remington Rand, as a way of scheduling large projects. At about the same time, the United States Navy's Polaris missile programme developed a close cousin, PERT.
Finding the path takes two walks through the network. Walking forward from the start, work out the earliest each task can begin: the latest finish of everything it waits for. The last task's earliest finish is the project's length. Then walk backward from that end date to find the latest each task can finish without delaying it. Tasks whose earliest and latest dates are the same have no room, and they form the critical path. Say task A takes 3 days, then B (5 days) and C (2 days) run side by side, and D (4 days) waits for both. A, B and D make 12 days; C has 3 days to spare.
Here is the practical point. Speeding up C, or putting more people on it, changes nothing; only A, B or D can bring the end closer. Effort belongs on the path. But the path can move: if C slips by more than its spare time, it becomes critical itself, so the calculation is redone whenever the work changes.
Go deeper
PERT added something the critical path method left out: uncertainty. Each task got three estimates, an optimistic one, a most likely one and a pessimistic one, combined into an expected time that weighs the most likely four times as heavily as either extreme. The idea was to show not just one finish date but how sure anyone could be of it. Both methods rest on the same network of linked tasks, and both find the chain with no room to spare.
Overtime in the right place

Jalila manages a fruit juice factory near Agadir, Morocco, where an old bottling line had to be replaced during a two-week summer shutdown. The plan was tight, and her manager offered money for overtime. His instinct was to spend it on the electricians rewiring the labelling machine, because they looked the busiest.
Jalila laid out the tasks first. Removing the old filler took 2 days, installing the new one 6, and the test run 2: one chain of 10 days. The rewiring took 3 days, the new floor drain 3, and retraining the operators 4, all running beside that chain with days to spare. Overtime for the electricians would have finished their part early and left the line no closer to running. She spent the money on an extra shift of fitters for the filler installation instead, which cut it to 5 days. The test run finished a day before the shutdown ended.
Try this today Look at something you must finish by a date. Which steps follow one after another with no way round? Add them up and compare with the date.
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “The Critical Path.” https://quest2plan.com/learn/lesson/the-critical-path. Accessed 29 November 2026.
Sources
- Critical path method — How the method works and its origin with Morgan Walker of DuPont and James Kelley of Remington Rand.
- Program evaluation and review technique — PERT, developed for the US Navy's Polaris programme in 1958, with its three time estimates.