Make the Work Visible

In one line Put every piece of work on a card in a column for its stage, so the whole team can see the flow.

Much of the work in an office or on a ward cannot be seen. A plan on the wall shows the big milestones, but the daily stream of requests, fixes, forms and favours lives in inboxes and in people's heads. Nobody can tell what is waiting, who is overloaded or what has been stuck for a fortnight, so each person judges the load by their own small share of it.

A kanban board puts that stream where everyone can see it. The word is Japanese for a signboard, and earlier in the course Just in Time showed how Toyota used kanban cards from the 1950s to signal what the next step needed. Draw a column for each stage that work really passes through, such as waiting, doing, checking and done; give each piece of work its own card; and move the card as the work moves. Software teams began adapting the idea in the 2000s, and many hospital wards keep a board showing each bed, each patient and what they are waiting for: a scan, a review, a lift home.

The first week is often the most instructive. Cards appear that nobody knew about: the urgent favour for the director, the report that has sat in checking for a month. The doing column turns out to hold far more than anyone guessed. Cards pile up in one place, usually where work waits for one person or one signature. And the team starts reading the board together, from the right: what is nearly done, and what is stuck.

A board shows the truth only if the truth goes on it. When hidden work stays off, or done means different things to different people, the board looks calm while people are swamped. And seeing a pile is not the same as shrinking it. That needs a limit on how much is started at once.

Seventy cards on the workshop wall

Illustration: Seventy cards on the workshop wall

Meseret leads the maintenance team at a regional hospital in Hawassa, Ethiopia. Requests reach her six technicians by phone, on scraps of paper and in the corridor, and the wards complain that broken beds and dripping taps wait for weeks. The technicians say they are run off their feet. Both seem true, and nobody can say where the time goes.

One Monday she marks four columns on the workshop wall: requested, being fixed, waiting for parts, and done. Every job gets a card with the ward and the date. By Friday there are seventy cards, twenty more than anyone expected, and eleven sit under waiting for parts, some since the rains began. The technicians had been starting a new job whenever a part was missing, so each had several open at once. The board does not fix that yet, but for the first time the wards, the technicians and the storekeeper are looking at the same picture.

Try this today Write each thing you have started but not finished on its own note. Count them, and see which has waited longest.

In the Toolkit, step by step: Kanban board →

Question 1 of 2

A municipal planning office in Lima, Peru, puts up a board of columns. After a week, Marlon notices that a third of all the cards sit in a column headed 'with the legal team'.

What is the board most likely showing the office?

Question 2 of 2

A charity's office in Kigali, Rwanda, starts a board for its small team. Odette, the director, asks staff to leave her own urgent requests off it, since 'those just get done'.

What is wrong with Odette's request?

Cite or share this lesson

A plain reference you can paste into notes or an essay:

Quest2Plan. “Make the Work Visible.” https://quest2plan.com/learn/lesson/make-the-work-visible. Accessed 29 November 2026.

Sources
  • Kanban board — How a board of columns and cards shows work moving through the stages of a process.
  • Kanban — The Japanese word for a signboard, and Toyota's production cards from the machine shop of 1953.