Traps · Judging people and work
Brooks's law
Adding people to a late project can make it later, because newcomers need training and every extra person adds conversations.
What it is
Fred Brooks managed the development of OS/360, the operating system for IBM's System/360 computers, in the 1960s. In The Mythical Man-Month (1975) he wrote that adding manpower to a late software project makes it later. Newcomers must be taught by the people who are already behind, the work has to be split again, and the number of possible conversations grows quickly: four people make six pairs, ten make forty-five. Some work cannot be split at all; as Brooks put it, bearing a child takes nine months however many women are assigned. He himself called the law an oversimplification.
An example
A charity's warehouse is three weeks behind packing winter kits for refugee camps. The director sends twelve volunteers from the office. On their first day the four experienced packers stop to show them the checklists, the stock system and where everything lives, and two newcomers pack the wrong sizes, which must be unpacked. The first week's output falls. By the third week the newcomers are useful, but the kits ship later than if the help had come at the start, or had been given simpler, separate jobs.
How to spot it
A plan to recover a delay that rests mainly on hiring or borrowing people. Experienced people spending their days explaining rather than doing. Work cut into ever smaller pieces so that newcomers have something to do.
The way out
Add people early, or add them to work that can stand apart. When a project is late, first cut or reorder scope, remove blockers and protect the people who know the work; bring in help for separate, quickly learned tasks that need little of the core team's time.
When it is wise
Brooks's law applies less where tasks are simple and separate: more hands do speed up a harvest, a wall of sandbags or a mailing. Adding people early in a long project, with time to learn, often pays off.
Printable sheet of every technique
Cite or share this page
A plain reference you can paste into notes or an essay:
Quest2Plan. “Brooks's law.” https://quest2plan.com/learn/ideas/traps/brooks-law. Accessed 29 November 2026.