Why Hidden Padding Fails

In one line Time quietly added to each task tends to be spent anyway; one visible reserve shared by the team protects the date.

Asked for an estimate, most people quietly add something. The tiler says four days and thinks three; the analyst says two weeks and thinks eight working days. Each extra is small and feels prudent. Across a plan of thirty tasks it adds up to a great deal of hidden time, and the odd thing is that projects built this way still run late.

Two habits explain why. Earlier in the course, Starting at the Last Minute described student syndrome, starting work only when the deadline feels close, and Parkinson's law, work swelling to fill the time allowed. Padding feeds both. Someone who knows a task has a spare day starts a day later, or polishes for a day longer, and the cushion is gone before any trouble arrives. A task that finishes early is rarely handed on early, since nobody wants to show their estimate was generous, while a task that finishes late passes its lateness down the line. Gains are lost and losses add up.

Eliyahu Goldratt's critical chain method, set out in his 1997 novel Critical Chain, offers an alternative now used in many fields. Estimate each task honestly, at a figure it has about an even chance of meeting. Take the private padding out, and gather the safety into one visible buffer at the end of the project, with smaller buffers where side paths join the main one. The date at the end of the buffer is the date promised, and the team watches how fast the buffer is being used against how far the work has come.

A shared buffer works only with trust. Nobody may be blamed when their task runs past an estimate that was meant to be missed half the time, and leaders must not quietly cut the buffer as soon as they see it. Where that trust is missing, people will go on padding in secret, and with some reason.

The reserve on the wall

Illustration: The reserve on the wall

Rubén organizes the yearly congress of a farmers' federation in Cartagena, Colombia. Last year his plan had twenty-two tasks, each with a deadline set by the person doing it, and every one, he later learned, carried a few spare days. The venue contract, the speakers' travel and the printed programmes all finished on or just after their deadlines, and the programmes reached the venue the night before opening.

This year Rubén asked each person for the time a task would take if nothing unusual happened, and promised that missing it would not count against them. The estimates came back about a third shorter. He added up the spare time people admitted to, kept half of it as a single reserve of three weeks before the congress, and drew it as a bar on the office wall. Each Monday the team shaded what the reserve had lost. The speakers' visa letters ate eight days of it and small delays three more; everything was ready with ten days to spare.

Try this today Look at a deadline you set yourself. If it hides spare days, write them down separately as a reserve and set the task date honestly.

Question 1 of 2

In Iloilo, the Philippines, a provincial office moving to a new building gives each of its eight teams a deadline with a hidden spare week. Every team finishes in the last two days of its time.

Which explanation fits this pattern best?

Question 2 of 2

Nadir is planning a 600-guest wedding in Lahore, Pakistan. He keeps a two-week reserve at the end of the plan, but writes it in as 'final checks' and tells no one it is spare.

What is the weakness in how Nadir keeps his reserve?