Lesson · 6 min Stretch

Who Steers?

In one line A steering group exists to decide, unblock and ask hard questions; many only listen to reports, and then nobody steers.

Some decisions are too big for a project to make for itself: more money, a later date, a cut in scope, a clash with another department. A steering group, also called a project board or steering committee, exists to make them. PRINCE2, a method from the British government, gives its board people who speak for the business, the users and the suppliers, and sets limits within which the project manager acts alone. When a limit looks likely to be broken, the decision goes back up to the board.

A good steering group does three things. It decides, and does so quickly when asked. It unblocks: a board member can get a permit moving, settle a quarrel between departments or lend staff, which the project manager cannot. And it asks hard questions: is the case still sound, what are we not being told, should this stop. Earlier, The Sponsor showed what one committed person at the top can do; a board spreads that work across the people whose support the project needs.

Many boards only listen. Meetings become a run of status slides, every report is green, and busy senior people nod and move on. Earlier in the course, Green Outside, Red Inside showed how reports drift from the truth; a board that only receives reports invites the drift. Signs of a board that steers: a short paper sent ahead, problems discussed before progress, decisions recorded at every meeting, and members who have seen the work for themselves.

Size and balance matter. A board of fifteen tends to listen; a board of four or five can decide. There is a tension too: a board that steps in at every turn takes the work away from its manager, while one that never steps in is decoration. Good boards agree in advance which questions are theirs.

A board that started deciding

Illustration: A board that started deciding

Mpho chairs the project board for a new footbridge over a river in Mthatha, South Africa, linking a township to a school and a clinic. For six months the board met monthly to hear the same pleasant report. Then the project manager mentioned, on the last slide, that the electricity company had still not moved a power line in the bridge's path, and that the delay was now ten weeks.

Mpho changed the meetings. The manager now sends two pages two days ahead, and the meeting opens with problems, each ending in a decision or a named member who will act. The board member from the municipality phones the electricity company's regional director the next morning, and the line is moved within three weeks. At the following meeting the board decides to drop a decorative arch to recover the lost time, and records why.

Try this today Look at the last record of a steering meeting you know. Count the decisions in it, and compare with the number of reports received.

Question 1 of 2

Kifah is a trustee of a refugee education charity in Amman, Jordan. At each trustees' meeting the director presents twenty slides of progress, the trustees thank her, and the meeting closes. In a year the minutes record no decisions.

What is this board failing to do?

Question 2 of 2

Luis manages a water-pipe project in Quito, Ecuador. His board has given him a limit: he may let the finish date slip by up to three weeks without asking. A supplier's delay now looks set to push it back by seven.

What should Luis do?

Cite or share this lesson

A plain reference you can paste into notes or an essay:

Quest2Plan. “Who Steers?.” https://quest2plan.com/learn/lesson/who-steers. Accessed 29 November 2026.