Lesson · 6 min Steady
What Waiting Costs
In one line Put a price on each week a piece of work is late, and let that price decide what goes first.
Every project plan has a date, but few say what it costs to miss it. Teams talk about a week's slip as if it were free, or as if its only cost were extra wages. Donald Reinertsen, an American writer on product development, argued that the most important missing number is the cost of delay: the money, or other value, lost for each week a result arrives late.
The idea runs through his work, from Developing Products in Half the Time (1991), written with Preston Smith, which has a chapter on putting a price on time, to The Principles of Product Development Flow (2009). There he made it the one economic figure a team should work out if it works out no other. He reported that about 85 per cent of the product developers he asked did not know theirs, and that guesses made without a calculation could differ by as much as fifty to one.
A rough figure is often enough. A new seed variety that misses the planting season loses a year's sales; a factory upgrade that saves fuel loses that saving for every week it waits; a grant report may cost nothing until its deadline, then a great deal. Once the costs are known, the order of work changes. One common rule, usually called weighted shortest job first, divides each job's weekly cost of delay by the weeks it will take and starts with the highest, so short, costly jobs jump the queue.
Earlier in the course, Little's Law showed that more work in a system means longer waits; cost of delay puts a price on those waits. The method has critics. Its figures rest on forecasts of sales or savings that may be wrong, and a money value for safety or goodwill can feel false. Its defenders reply that a rough number argued over in the open beats a silent assumption that waiting costs nothing.
Go deeper
The shape of a cost of delay matters as much as its size. Some delays cost the same every week, like a fuel saving postponed. Some cost almost nothing and then everything, like a fixed deadline. And some cost more than they seem, because arriving late shortens the whole period of earnings: a product that reaches a market after a rival may never win the customers the rival took first. Sketching each job's cost as a line over time helps a team see which kind it faces.
Two projects, one team

Mamadou heads engineering at a fruit-processing plant near Thiès, Senegal. Two projects wait for his team of four. Heat recovery for the dryers would save about two million CFA francs a week in fuel and needs six weeks. New packaging for an export order of dried mango, which a buyer has said will bring in about ten million francs a week once it starts, needs three.
For years the plant has chosen by who argued loudest, and the heat recovery, the managing director's favourite, would have gone first. Mamadou does the sums instead. Doing the packaging first delays the fuel saving by three weeks, a cost of about six million francs. Doing the heat recovery first delays the export by six weeks, a cost of about sixty million. Dividing each weekly cost by the weeks needed points the same way. The packaging goes first, and the managing director, shown the figures, agrees.
Try this today Pick two jobs waiting on your list. Guess roughly what each loses for every week it waits, and do the dearer one first.
Cite or share this lesson
A plain reference you can paste into notes or an essay:
Quest2Plan. “What Waiting Costs.” https://quest2plan.com/learn/lesson/what-waiting-costs. Accessed 29 November 2026.
Sources
- Cost of delay — Cost of delay as value lost per unit of time, Reinertsen's argument for working it out, and dividing it by duration to set priorities.
- Developing Products in Half the Time — The publisher's page for Smith and Reinertsen's book, with its chapter on putting a price tag on time.