What Ninety Per Cent Done Hides

In one line Per cent complete is usually a guess; counting items that are wholly finished shows progress more honestly.

The most common number in a project report is also one of the least trustworthy. 'Ninety per cent done' sounds exact, yet it is usually a judgement made by looking at effort spent, money spent or how much of the thing can be seen. Earlier in the course, The Last Ten Per Cent showed how such figures climb fast and then stall, because the joining, testing and paperwork at the end were never counted. So what should a report show instead?

Fred Brooks, writing about large software projects in The Mythical Man-Month in 1975, noticed that coding was reported as ninety per cent finished for about half of the coding time. His cure was to report against milestones so concrete that nobody could argue about whether they had happened: a specification signed, a program that passes all its tests. The same holds on a building site. 'The third floor is seventy per cent done' invites debate; 'slabs poured on floors one to three, plastering finished on floor one' does not.

The usual better measure is a count of finished items, where an item counts only when it is wholly done by an agreed definition: the room handed over, the feature tested and released. Partly done work counts as zero. The count looks slow in the early weeks, because much is started and little finished, but it cannot sit at ninety per cent for months. Small items help, so that the count moves often and a stalled one shows up quickly. Earned value, met in Earned Value in Plain Words, can use the same rule.

Counting has costs of its own. Items differ in size, so ten small finished items may hide one large untouched one, and a team may start picking easy items to make the count rise. The count is a better question rather than a perfect answer: what is truly finished, and what is left?

Twelve classrooms, none finished

Illustration: Twelve classrooms, none finished

Ebrahim managed the fitting out of a new twelve-classroom school in Sohar, in Oman. For five weeks the contractor's report said 84, 88, 90, 91 and 91 per cent complete, and the ministry's officer began to ask why the number had stopped. Nobody on site could say what the missing nine per cent was.

Ebrahim pinned a chart of the twelve classrooms to the site office wall. Each had a short list: wiring, plaster, paint, doors, final electrical check, inspection. A room counted as finished only when every line was ticked. The first count was zero out of twelve, which alarmed the ministry, but the chart also showed why: every room was waiting on the same two things, the electrician's final connections and the fire doors, still on order. Ebrahim had the electrician finish rooms one at a time instead of all twelve at once, and chased the doors. Three weeks later four rooms were handed over, and the count gave a date the ministry could check for itself.

Try this today Take one task you would call nearly done. Write down what 'finished' means for it, and say honestly whether it is finished yet.

Question 1 of 2

A team building a tax-filing app for the city council of Ho Chi Minh City, Vietnam, reports that it is 85 per cent complete, because 85 per cent of the budgeted hours have been used.

What is the main weakness of this figure?

Question 2 of 2

Delfina oversees the rebuilding of a covered market with twenty stalls in Cusco, Peru, for the city council.

Which progress report would give the council the clearest picture?

Cite or share this lesson

A plain reference you can paste into notes or an essay:

Quest2Plan. “What Ninety Per Cent Done Hides.” https://quest2plan.com/learn/lesson/what-ninety-percent-hides. Accessed 29 November 2026.

Sources
  • Ninety-ninety rule — The joke about the last ten per cent of the work taking as long as the first ninety.
  • The Mythical Man-Month — Fred Brooks's 1975 essays on software projects, including how progress is tracked against milestones.