What Must Come First

In one line Dependencies say which pieces of work must wait for which, and the order of a plan comes from them.

Some pieces of work cannot begin until others are finished. The walls go up before the roof, the plaster dries before the paint goes on, and nobody tiles a floor that has not been laid. Planners call these links dependencies. Once a project has been broken into pieces, the next question is their order, and the order comes from asking, of every piece, what it has to wait for.

Most links are of one kind, finish to start: one task must end before the next can begin. Some are looser. In a start-to-start link, the second task may begin once the first has begun, as when painters start on the first finished room while the plasterers move on. In a finish-to-finish link, one task cannot end until another has: the checking of the wiring is not complete until the wiring is. Some links also carry a wait with no work in it, such as the days plaster needs to dry.

It helps to know why each link exists. Some come from the nature of the work: a cupboard cannot hang on a wall that is not there. Some come from people or tools: one tiler cannot work in two rooms at once. Others are choices or habits, such as always doing the bedroom before the hall. Under pressure the first kind cannot bend, but the last kind can.

Many delays that seem to come from nowhere were dependencies nobody wrote down. A stone worktop cannot be measured until the cupboards are fixed, and the cutting takes days; a permit must arrive before an old wall comes down. Asking what each task waits for is dull work, but it finds these links while they are still cheap. A long list of links is hard to see whole, though, which is why planners draw them.

The worktop nobody had counted

Illustration: The worktop nobody had counted

Lamia was refitting the kitchen of her flat in Sousse, Tunisia, and her builder promised three weeks. Before work began she wrote each job on a slip of paper: strip the old units, move the sink pipes, rewire, plaster, fit the cupboards, fit the stone worktop, tile, paint, plug in the cooker. Then she asked the builder, slip by slip, what each one waited for.

Most answers were obvious. One was not. The stone-cutter could measure only once the cupboards were fixed, and then needed ten days to cut the stone, and the tiles above the worktop had to wait for the stone. The builder's three weeks had assumed the worktop would arrive the day after the cupboards. Lamia booked the stone-cutter's visit for the afternoon the cupboards were finished, and asked the painter to do the other three walls during the ten days. The kitchen took four weeks, but she knew about the fourth week on the first day.

Try this today Pick one job you have this week and ask of each step: what has to be finished before this can start? Write down any answer that surprises you.

Question 1 of 2

Builders adding a storey to a health clinic in Battambang, Cambodia, cannot mount the solar panels until the roof frame has been strengthened.

Which kind of link is this?

Question 2 of 2

Kemal is planning the repair of a village hall near Konya, Turkey. The plaster on the new wall will be finished on Monday, and his plan says the paint goes on ____.

Which entry fits the link between the plaster and the paint?