What a Failed Project Teaches

In one line Projects fail in ordinary, repeating ways, so a review that asks what happened, not who is to blame, can teach.

Most projects do not fail in strange new ways. They fail in the ways this week has described: estimates drawn from the best case, goals pictured differently, warnings left unspoken, tasks owned by everyone, time used up before work begins. That is discouraging at first, and then encouraging, because a failure that repeats is one a team can learn to see. A missed goal is information about how the work is done.

The obstacle is blame. When something goes wrong, the natural question is who did it, and once a culprit is found the inquiry tends to stop. People learn to hide mistakes, and the conditions that produced the mistake stay in place for the next person. Earlier in the course, The System, Not the Person set out W. Edwards Deming's case that most problems come from how work is set up. A review that asks what happened and why, rather than whose fault it was, follows the same thought.

Armies, hospitals and airlines have built habits around this. The United States Army developed the after-action review, in which a team compares what it meant to happen with what did happen, and asks why, while events are fresh. Software teams speak of blameless post-mortems. Health services speak of a just culture, in which honest error is treated as a chance to learn, while deliberate misconduct can still be dealt with. The questions are much alike: what did we expect, what happened, why the difference, and what will we do next time?

Reviews have their critics. Held too often they become ritual, and their lists of lessons are filed and forgotten. A review earns its time only when something changes afterwards, and the course returns later in the year to how to run one well.

Go deeper

A blame-free review is not the same as a consequence-free one. Writers on just culture draw a line between honest error, which a review should learn from, and wilful misconduct, which may still call for discipline. The line protects both sides: people can admit a slip without fear, and colleagues can trust that someone who cut corners on purpose will not hide behind the review. Where exactly to draw it is debated, and different services draw it differently.

Twenty-two wells out of forty

Illustration: Twenty-two wells out of forty

Imani leads a small research group at a university in Dar es Salaam, Tanzania, testing whether a cheap filter removes bacteria from well water. The group had promised its funder results from forty village wells by March. By March it had samples from twenty-two.

At the review, Imani began with a rule: nobody would be named as the cause. On a whiteboard she wrote three questions: what did we plan, what happened, and why the gap. The answers came quickly once no one was defending themselves. Samples had to reach the lab within a day, but the group's only vehicle was booked for teaching on two days each week, and no one had owned the job of reserving it. Next season the group booked a vehicle for the whole sampling period, with one person in charge of the bookings.

Try this today Pick something that went wrong recently. Write what you expected, what happened and why they differed, without naming anyone at fault.

Question 1 of 2

A software team in Montevideo, Uruguay, misses a release date by three weeks. In the review, the lead, Hernán, opens by asking which developer wrote the code that held things up.

What is the likely cost of opening the review this way?

Question 2 of 2

Huda is running a review for her team in Doha, Qatar, after their stand at a trade fair opened a day late.

Which order of questions follows the usual review?

Cite or share this lesson

A plain reference you can paste into notes or an essay:

Quest2Plan. “What a Failed Project Teaches.” https://quest2plan.com/learn/lesson/what-failure-teaches. Accessed 29 November 2026.

Sources
  • After-action review — The US Army's method of comparing intended and actual results, without assigning blame.
  • Just culture — Asking what went wrong rather than who caused it, while still dealing with wilful misconduct.
  • Postmortem documentation — Project post-mortems: finding the causes of a failure so it is not repeated.