Velocity and Its Abuse

In one line Velocity helps a team forecast its own work; used to compare or push teams, it inflates and stops meaning anything.

Velocity is the amount of work a team finishes in one cycle, usually a sprint of one or two weeks, counted in finished items or in story points, the team's own relative sizes for pieces of work. A team that finished 30 points, then 26, then 32 can expect roughly 30 next time and plan to match. Earlier in the course, Last Time, How Long? showed the value of forecasting from your own record; velocity is that record kept sprint by sprint, and a burn-up chart, described in Burn-down and Burn-up Charts, is velocity drawn over time.

The trouble starts when the number leaves the team. Points are a private currency: one team's 5 is not another's, because each team sized its work against its own examples. Comparing teams by velocity is like comparing prices in two currencies with no exchange rate. And when a manager demands that velocity rise, the cheapest way to raise it is not to work faster but to estimate larger. A piece of work that was a 3 last month becomes a 5. The chart climbs, nothing more is delivered, and the number no longer forecasts anything.

The other ways to raise velocity are worse. Testing gets thinner, tidying of the code is put off, and items are called done before they truly are, so faults pile up for later sprints. Helping another team, teaching a newcomer or fixing a problem nobody estimated all earn no points, so they quietly stop.

Used well, velocity is a planning aid owned by the team: a range rather than a single figure, read beside quality measures such as faults found after release, and never turned into a target or a ranking. The general law behind its abuse is the subject of a later lesson this week.

Twice the points, the same forms

Illustration: Twice the points, the same forms

Fidel ran the digital services unit of a provincial government in Cebu, the Philippines, where three teams were turning paper permits into online forms. His director asked for a monthly table ranking the teams by velocity, with a certificate for the top one. Within three months, one team's velocity had doubled, from 25 points a sprint to 50.

The number of forms released to the public had not changed: about four a month. Complaints about broken forms had risen. Fidel sat down with the team and went through their old and new estimates. Nobody had lied. Each estimate had simply crept up, a 3 becoming a 5, and testing had been cut short to get items over the line before the sprint ended. Fidel dropped the ranking. Each team kept velocity on its own wall for planning, and the monthly report to the director showed forms released and faults reported by the public instead.

Try this today Look at one number your work is judged by. Ask how someone could raise it without doing any more useful work.

Question 1 of 2

Two teams in a university's computing office in Monterrey, Mexico, report velocities of 40 and 20 points a sprint. The dean asks why the second team is half as productive.

How should the dean be answered?

Question 2 of 2

Eun-ji leads a team in a hospital's records office in Busan, South Korea. After the hospital set a growth target, her team's velocity rose by half over two quarters, but the work handed to the wards has not increased.

What most likely explains the rising number?

Cite or share this lesson

A plain reference you can paste into notes or an essay:

Quest2Plan. “Velocity and Its Abuse.” https://quest2plan.com/learn/lesson/velocity-and-its-abuse. Accessed 29 November 2026.

Sources
  • Velocity (software development) — What velocity measures, how teams forecast with it, and how it is inflated when used as a target.
  • Planning poker — One way teams size work together in relative units such as story points.